10801 1/2 N WESCOTT AVE 91040

Certificate Information: 10801 1/2 N WESCOTT AVE 91040

Application / Permit
23014-20000-02034
Plan Check / Job No.
B23VN06722
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH ADDITION TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 6/13/2023
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 JESSE ARELLANO
Corrections Issued 5/27/2023 JESSE ARELLANO
Building Plans Picked Up 6/2/2023 APPLICANT
Plan Check Approved 6/13/2023 ALEC MOUSAKHANIAN
Issued 6/13/2023 APPLICANT
CofO in Progress 9/17/2025 WILLIAM WREN
CofO Issued 10/2/2025 RUBEN SALAS
Permit Finaled 10/2/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/7/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 6/7/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 6/7/2023 NIKKI ZULUETA
Sewer availability Cleared 6/7/2023 NIKKI ZULUETA
Grading Pre-Inspection Cleared 6/13/2023 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/8/2024 Partial Approval WILLIAM WREN
Excavation/Setback/Form/Re-Bar 4/18/2024 Approved WILLIAM WREN
Pre-Inspection 4/18/2024 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 5/10/2024 Partial Approval WILLIAM WREN
Green Building Rough 5/10/2024 Not Ready for Inspection WILLIAM WREN
Wood Frame 5/10/2024 Not Ready for Inspection WILLIAM WREN
BUILDING-Rough-Frame 5/31/2024 Not Ready for Inspection WILLIAM WREN
Green Building Rough 5/31/2024 Approved WILLIAM WREN
PLUMBING-Rough 5/31/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 8/12/2024 Approved WILLIAM WREN
ELECTRICAL-Rough 8/12/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Approved WILLIAM WREN
Underground Mechanical 8/12/2024 Partial Approval WILLIAM WREN
Wood Frame 8/12/2024 Not Ready for Inspection WILLIAM WREN
Insulation 9/3/2024 Approved WILLIAM WREN
Shower Pan 9/3/2024 Approved WILLIAM WREN
Drywall Nailing 9/12/2024 Approved WILLIAM WREN
Gas Test 10/17/2024 Approved WILLIAM WREN
Sewer 10/17/2024 Approved WILLIAM WREN
Underground Mechanical 10/17/2024 Approved WILLIAM WREN
Final 5/30/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 5/30/2025 Approved DAVID ANDERSON
Green Building Final 5/30/2025 Not Ready for Inspection DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 5/30/2025 Approved DAVID ANDERSON
Final 6/6/2025 Corrections Issued WILLIAM WREN
Green Building Final 6/6/2025 Approved WILLIAM WREN
Final 7/25/2025 OK to Issue CofO WILLIAM WREN
Service/Power Release 7/25/2025 Approved WILLIAM WREN