5845 N MELVIN AVE 91356
Certificate Information: 5845 N MELVIN AVE 91356
- Application / Permit
- 23014-20000-02030
- Plan Check / Job No.
- B23VN06711
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN PROPOSED 22'-5" X 28'-2" ADDITION AT REAR AND 14'-11" X 33'-10" ADDITION AT FRONT AND REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 10/18/2023
- Issuing Office
- Current Status
- Issued on 10/18/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2023 | RAPHAEL ROSAS |
| Corrections Issued | 6/23/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 6/30/2023 | STEVEN KIM |
| Applicant returned to address corrections | 9/27/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/5/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 10/13/2023 | RAPHAEL ROSAS |
| Issued | 10/18/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/17/2023 | CARLOS AGUILERA |
| ZA Case | Cleared | 7/18/2023 | RUBEN VASQUEZ |
| Low Impact Development (LID) | Cleared | 10/5/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 10/5/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/5/2023 | NIKKI ZULUETA |
Contact Information
| Architect | Heifetz,, Daniel Eli; Lic. No.: NA30912 | , |
| Contractor | Ice General Builder Inc; Lic. No.: 696333-B | , |
| Engineer | Cox,, Steven Jeffrey; Lic. No.: C48940 | 130 MAGELLAN ST THOUSAND OAKS, CA 91360 |
| Engineer | Cox,, Steven Jeffrey; Lic. No.: NA48940 | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/11/2023 | Partial Approval | JON MCHUGH |
| Pre-Inspection | 12/22/2023 | Approved | JEFFREY PARD |
| Deputy Steel/Welding | 12/27/2023 | Conditional Approval | JON MCHUGH |
| Pre-Inspection | 12/29/2023 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 1/5/2024 | Conditional Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 1/8/2024 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 1/8/2024 | Partial Approval | JON MCHUGH |
| Deputy Reinf. Concrete | 1/9/2024 | Conditional Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 1/16/2024 | Approved | JON MCHUGH |
| Deputy Reinf. Concrete | 1/16/2024 | Approved | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 1/16/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 1/16/2024 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 1/16/2024 | Partial Approval | JON MCHUGH |
| Sewer | 1/16/2024 | Not Ready for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 1/24/2024 | Partial Approval | JON MCHUGH |
| Footing/Foundation/Slab | 1/24/2024 | Partial Approval | JON MCHUGH |
| Deputy Steel/Welding | 1/31/2024 | Conditional Approval | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 2/7/2024 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 2/7/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 3/12/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 3/12/2024 | Approved | VINCENT HANLEY |
| Sewer | 3/12/2024 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 4/5/2024 | Approved | JON MCHUGH |
| HVAC-Rough | 4/5/2024 | Approved | JON MCHUGH |
| Insulation | 4/5/2024 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 4/9/2024 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 4/9/2024 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 4/9/2024 | Approved | JON MCHUGH |
| Wood Frame | 4/9/2024 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 4/17/2024 | Approved | JON MCHUGH |
| Green Building Rough | 4/17/2024 | Approved | JON MCHUGH |
| Insulation | 4/17/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/17/2024 | Partial Approval | JON MCHUGH |
| Wood Frame | 4/17/2024 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/24/2024 | Approved | HENRY KIM |
| Shower Pan | 4/24/2024 | Corrections Issued | HENRY KIM |
| Drywall Nailing | 4/25/2024 | Partial Approval | HENRY KIM |
| Shower Pan | 4/25/2024 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 6/18/2024 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 6/18/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 6/25/2024 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 10/31/2024 | Corrections Issued | JON MCHUGH |
| Service/Power Release | 10/31/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 11/8/2024 | Approved | JON MCHUGH |
| HVAC-Final | 11/8/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 11/8/2024 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | JON MCHUGH |
| Smoke Detectors | 11/8/2024 | Approved | JON MCHUGH |
| Gas Test | 11/20/2024 | Approved | JON MCHUGH |
| PLUMBING-Final | 11/20/2024 | Approved | JON MCHUGH |
| Green Building Final | 11/27/2024 | Approved | JON MCHUGH |
| Final | 12/2/2024 | Not Ready for Inspection | JON MCHUGH |