20207 W PARTHENIA ST 91306
Certificate Information: 20207 W PARTHENIA ST 91306
- Application / Permit
- 23014-20000-02021
- Plan Check / Job No.
- B23VN06684
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert (E) detached garage into (N) ADU with addition per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/27/2023
- Issuing Office
- Current Status
- CofO Issued on 4/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2023 | AMY GUEVARRA |
| Corrections Issued | 6/9/2023 | AMY GUEVARRA |
| Plan Check Approved | 10/27/2023 | AMY GUEVARRA |
| Issued | 10/27/2023 | APPLICANT |
| CofO in Progress | 3/20/2024 | JEFFREY HARTLINE |
| Permit Finaled | 4/4/2024 | JOHN JANSON |
| CofO Issued | 4/4/2024 | JOHN JANSON |
| Permit Finaled | 4/4/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2023 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 6/30/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/30/2023 | ROMAN GUTIERREZ |
| Construction within easement | Cleared | 10/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erusu,, Praneet Reddy; Lic. No.: C87773 | 6310 GREEN VALLEY CIRCLE APT 309 CULVER CITY, CA 90230 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/31/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/31/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Pre-Inspection | 10/31/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/16/2024 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 1/16/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 1/16/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Wood Frame | 1/16/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 1/25/2024 | Approved | JEFFREY HARTLINE |
| Excavation/Setback/Form/Re-Bar | 1/25/2024 | Partial Approval | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 1/25/2024 | Corrections Issued | JEFFREY HARTLINE |
| PLUMBING-Rough | 1/25/2024 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 2/1/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/1/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Green Building Rough | 2/1/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Rough | 2/1/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 2/9/2024 | Approved | MORRIS JACKSON |
| Footing/Foundation/Slab | 2/9/2024 | Partial Approval | JEFFREY HARTLINE |
| Insulation | 2/9/2024 | Approved | MORRIS JACKSON |
| HVAC-Rough | 2/15/2024 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 2/20/2024 | Approved | GEVORK IPCHYAN |
| Final | 3/13/2024 | Corrections Issued | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 3/13/2024 | Approved | JEFFREY HARTLINE |
| Green Building Final | 3/13/2024 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 3/13/2024 | SGSOV Approved | JEFFREY HARTLINE |
| Smoke Detectors | 3/13/2024 | Approved | JEFFREY HARTLINE |
| Final | 3/20/2024 | OK to Issue CofO | JEFFREY HARTLINE |