10527-10529 N TINKER AVE 91042
Certificate Information: 10527-10529 N TINKER AVE 91042
- Application / Permit
- 23014-20000-01984
- Plan Check / Job No.
- B23VN06556
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 14'-1" X 21'-1 1/4" IRREGULAR SHAPED ADDITION AND CONVERT EXISTING ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) - PER WFPP
- Permit Issued
- Issued on 5/22/2024
- Issuing Office
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 5/27/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/15/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 5/21/2024 | GIOVANNY CHAVEZ |
| Issued | 5/22/2024 | APPLICANT |
| CofO in Progress | 10/11/2024 | WILLIAM WREN |
| CofO in Progress | 10/11/2024 | WILLIAM WREN |
| CofO in Progress | 10/11/2024 | WILLIAM WREN |
| Permit Finaled | 10/22/2024 | DANIEL ORRANTE |
| CofO Issued | 10/22/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/22/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/17/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/17/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 6/29/2023 | JONATHAN HOM |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2023 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 8/2/2023 | ERICK MARCHENA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/28/2024 | Conditional Approval | DAVID MATSON |
| PLUMBING-Rough | 5/29/2024 | Partial Approval | MATTHEW NELSON |
| Sewer | 5/29/2024 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/3/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2024 | Partial Approval | WILLIAM WREN |
| Wood Frame | 6/28/2024 | Corrections Issued | WILLIAM WREN |
| ELECTRICAL-Rough | 7/12/2024 | Approved | WILLIAM WREN |
| HVAC-Rough | 7/12/2024 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 7/12/2024 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 7/17/2024 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 7/17/2024 | Approved | WILLIAM WREN |
| Insulation | 7/18/2024 | Approved | WILLIAM WREN |
| Drywall Nailing | 7/24/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/24/2024 | Partial Approval | DAVID ANDERSON |
| Shower Pan | 7/29/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 8/1/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 8/7/2024 | Partial Approval | WILLIAM WREN |
| Interior/Exterior Lathing | 8/7/2024 | Approved | WILLIAM WREN |
| Final | 9/13/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 9/13/2024 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/13/2024 | SGSOV Not Ready | WILLIAM WREN |
| Smoke Detectors | 9/13/2024 | Approved | WILLIAM WREN |
| Final | 9/26/2024 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 9/26/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2024 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 10/11/2024 | Approved | WILLIAM WREN |