12051-12053 W RATNER ST 91605
Certificate Information: 12051-12053 W RATNER ST 91605
- Application / Permit
- 23014-20000-01937
- Plan Check / Job No.
- B23VN06448
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN : 33'-6" X 17'-0" ADDITION OF 1 STORY ADU TO (E) 2 STORY SFD PER LAMC 12.22 A.33(c) and (e), ALL WORK PER ENG.
- Permit Issued
- Issued on 6/9/2023
- Issuing Office
- Current Status
- CofO Issued on 3/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/22/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/23/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/1/2023 | ISIS ARGUETA |
| Plan Check Approved | 6/7/2023 | DANIEL YIP |
| Issued | 6/9/2023 | APPLICANT |
| CofO in Progress | 2/29/2024 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/8/2024 | RUBEN SALAS |
| CofO Issued | 3/8/2024 | RUBEN SALAS |
| Permit Finaled | 3/8/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/26/2023 | CARLOS AGUILERA |
| Miscellaneous | Cleared | 5/30/2023 | BRENNEN OBETO |
| Sewer availability | Cleared | 5/30/2023 | CARLOS AGUILERA |
| Tract Map conditions | Cleared | 5/30/2023 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Fernandez,, Samuel; Lic. No.: C70886 | 8225 BRIMFIELD AVE PANORAMA CITY, CA 91402 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/17/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Pre-Inspection | 8/18/2023 | Approved | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 9/8/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/8/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 10/5/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/5/2023 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 10/5/2023 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/5/2023 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/5/2023 | Approved | CHRISTOPHER ROJAS |
| Insulation | 10/18/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 10/18/2023 | Corrections Issued | THOMAS FINNILA |
| Drywall Nailing | 10/20/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/20/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/1/2023 | Order to Comply Issued | WILLIAM WREN |
| ELECTRICAL-Final | 2/7/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 2/7/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 2/7/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 2/16/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Green Building Final | 2/16/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/16/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 2/16/2024 | Approved | CHRISTOPHER ROJAS |