6628 N BABCOCK AVE 91606

Certificate Information: 6628 N BABCOCK AVE 91606

Application / Permit
23014-20000-01936
Plan Check / Job No.
B23VN06447
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 22'-1 1/4" x 27'-1 3/4" ADDITION AND REMODEL TO SFD (NFPA 13D FIRE SPRINKLERS REQUIRED)
Permit Issued
Issued on 8/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2023 APPLICANT
Assigned to Plan Check Engineer 5/22/2023 JEROME MAGAT PALMA
Corrections Issued 5/24/2023 JEROME MAGAT PALMA
Building Plans Picked Up 5/26/2023 APPLICANT
Plan Check Approved 8/7/2023 ISIS ARGUETA
Issued 8/18/2023 APPLICANT
CofO in Progress 4/2/2025 GAREN HAYRAPETYAN
Permit Finaled 4/10/2025 RUBEN SALAS
CofO Issued 4/10/2025 RUBEN SALAS
Permit Finaled 4/10/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/3/2023 SAMUEL LINN
Eng Process Fee Ord 176,300 Cleared 8/4/2023 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 8/4/2023 ROMAN GUTIERREZ
Sewer availability Cleared 8/4/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 2160 PARNELL WY      ALTADENA, CA 91001

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 11/8/2023 Partial Approval KIRK SANDERS
Underground Mechanical 11/8/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/9/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Corrections Issued KIRK SANDERS
Deputy Wood Construction 3/12/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/19/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/19/2024 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 3/27/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/27/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 3/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 3/27/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 4/9/2024 Approved JOSE AVILA
Interior/Exterior Lathing 4/9/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 4/12/2024 Approved JOSE AVILA
ELECTRICAL-Rough 4/12/2024 Approved JOSE AVILA
Drywall Nailing 5/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Shower Pan 5/7/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 5/10/2024 Approved RYAN SALAZAR
Insulation 5/10/2024 Approved RYAN SALAZAR
Final 4/2/2025 OK to Issue CofO GAREN HAYRAPETYAN
Footing/Foundation/Slab 4/2/2025 Approved GAREN HAYRAPETYAN
Green Building Final 4/2/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 4/2/2025 Approved GAREN HAYRAPETYAN
Smoke Detectors 4/2/2025 Approved GAREN HAYRAPETYAN