4629 N CAMELLIA AVE 91602

Certificate Information: 4629 N CAMELLIA AVE 91602

Application / Permit
23014-20000-01932
Plan Check / Job No.
B23VN06427
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan 1. 453 SQFT ADDITION TO FIRST FLOOR OF SFD WITH 2 NEW BEDROOMS, 1 NEW BATHROOM, AND NEW LAUNDRY ROOM. 2. 634 SQFT SECOND FLOOR ADDITION TO SFD 3. CONVERT EXIST. MUD ROOM INTO AN EXTENSION OF EXIST. KITCHEN. 4. CHANGE LAYOUT OF EXIST. BATHROOM IN NORTH SIDE OF SFD TO CLOSE EXIST. DOOR AND HAVE A NEW ENTRANCE FROM BEDROOM. 5. INCLUDING ELECRICAL, PLUMBING, AND MECHANICAL.
Permit Issued
Issued on 10/27/2023
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/19/2023 SUNMIN LEE
Corrections Issued 5/24/2023 SUNMIN LEE
Quality Review Completed 6/22/2023 JOHN FRANCIA
Applicant returned to address corrections 8/3/2023 SUNMIN LEE
Applicant returned to address corrections 8/16/2023 SUNMIN LEE
Applicant returned to address corrections 8/22/2023 SUNMIN LEE
Plan Check Approved 9/14/2023 SUNMIN LEE
Issued 10/27/2023 APPLICANT
CofO in Progress 2/20/2025 CHRISTOPHER ROJAS
CofO in Progress 2/20/2025 CHRISTOPHER ROJAS
CofO in Progress 2/26/2025 CHRISTOPHER ROJAS
Permit Finaled 3/13/2025 RUBEN SALAS
CofO Issued 3/13/2025 RUBEN SALAS
Permit Finaled 3/13/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/5/2023 CARLOS AGUILERA
Sewer availability Cleared 6/5/2023 CARLOS AGUILERA
Specific Plan Cleared 7/11/2023 CHRISTIAN PEARSON
Low Impact Development (LID) Cleared 7/20/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/21/2023 JOHN LIN

Contact Information

Contractor Universal Home Design Inc; Lic. No.: 826744-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/8/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 1/16/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 1/23/2024 Approved CRAIG DAVIS
BUILDING-Rough-Frame 4/8/2024 Conditional Approval CHRISTOPHER ROJAS
PLUMBING-Rough 4/8/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/23/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 4/23/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 4/24/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/25/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/23/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Rough 5/23/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 5/29/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Partial Approval CHRISTOPHER ROJAS
MERV13>=Rough 5/29/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 6/27/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 6/27/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/16/2024 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 8/16/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 8/16/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 8/16/2024 Corrections Issued CHRISTOPHER ROJAS
MERV13>=Rough 8/16/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/16/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 9/16/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 9/16/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/16/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 9/16/2024 Approved CHRISTOPHER ROJAS
Insulation 9/19/2024 Corrections Issued CHRISTOPHER ROJAS
Drywall Nailing 9/25/2024 Partial Approval CHRISTOPHER ROJAS
Drywall Nailing 9/30/2024 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 9/30/2024 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 1/29/2025 Partial Inspection CHRISTOPHER ROJAS
Final 1/29/2025 Corrections Issued CHRISTOPHER ROJAS
MERV13>=Final 1/29/2025 Approved CHRISTOPHER ROJAS
PLUMBING-Final 1/29/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/29/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 1/29/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 2/18/2025 Approved CHRISTOPHER ROJAS
Final 2/18/2025 OK to Issue CofO CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 2/18/2025 Approved CHRISTOPHER ROJAS
Final 2/20/2025 Corrections Issued CHRISTOPHER ROJAS