21228 W VELICATA ST 91364

Certificate Information: 21228 W VELICATA ST 91364

Application / Permit
23014-20000-01918
Plan Check / Job No.
B23VN06397
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE WITH 18'-2" X 19'-0" ADDITION TO A DETACHED (613 S.F ) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) AND 10 S.F COVERED ENTRY. WORK DONE PER ENGINEERING.
Permit Issued
Issued on 9/29/2023
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/30/2023 MIROOSH KHACHATOORIAN
Corrections Issued 5/31/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 8/30/2023 MIROOSH KHACHATOORIAN
Issued 9/29/2023 APPLICANT
CofO in Progress 8/29/2025 JOHN HAYES
Permit Finaled 1/28/2026 JOHN JANSON
CofO Issued 1/28/2026 JOHN JANSON
Permit Finaled 1/28/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/5/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 6/5/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 6/7/2023 NIKKI ZULUETA
Sewer availability Cleared 6/7/2023 NIKKI ZULUETA
Construction near power lines Cleared 8/21/2023 RIDWAN HARDY
Grading Pre-Inspection Cleared 8/29/2023 MIROOSH KHACHATOORIAN

Contact Information

Contractor Vision Construction; Lic. No.: 759147-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 10/10/2023 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 10/16/2023 Corrections Issued PETER FOLLING
PLUMBING-Rough 10/16/2023 Partial Approval PETER FOLLING
Footing/Foundation/Slab 10/31/2023 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Approved JOHN KIDWELL
Rough-Elec/Plmb/HVAC 1/12/2024 Approved JOHN KIDWELL
Underground Mechanical 1/12/2024 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 1/18/2024 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 2/7/2024 Approved JOHN KIDWELL
Drywall Nailing 2/7/2024 Approved JOHN KIDWELL
Green Building Rough 2/7/2024 Approved JOHN KIDWELL
Insulation 2/7/2024 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 2/7/2024 Approved JOHN KIDWELL
Shower Pan 2/28/2024 Approved MORRIS JACKSON
Final 3/21/2025 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Ready JOHN HAYES
Smoke Detectors 3/21/2025 Not Ready for Inspection JOHN HAYES
Final 6/5/2025 Corrections Issued JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 6/5/2025 SGSOV Approved JOHN COLEMAN
Smoke Detectors 6/5/2025 Not Ready for Inspection JOHN COLEMAN
Final 6/26/2025 Corrections Issued JOHN HAYES
Smoke Detectors 6/26/2025 Approved JOHN HAYES
Final 8/19/2025 Corrections Issued JOHN HAYES
Special/Order Compliance 8/19/2025 Not Ready for Inspection JOHN HAYES
Final 8/29/2025 OK to Issue CofO JOHN HAYES