8457 N RINCON AVE 91352

Certificate Information: 8457 N RINCON AVE 91352

Application / Permit
23014-20000-01894
Plan Check / Job No.
B23VN06316
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Patio addition to (E) single family dwellling
Permit Issued
Issued on 10/4/2023
Issuing Office
Current Status
CofO Issued on 12/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2023 APPLICANT
Assigned to Plan Check Engineer 6/2/2023 EDWIN ESPIN
Corrections Issued 6/3/2023 EDWIN ESPIN
Applicant returned to address corrections 6/29/2023 EDWIN ESPIN
Applicant returned to address corrections 7/17/2023 DANIEL SMILEY
Plan Check Approved 10/1/2023 SHANGQIN XIE
Issued 10/4/2023 APPLICANT
CofO in Progress 12/6/2023 MATTHEW NELSON
CofO Issued 12/19/2023 RUBEN SALAS
Permit Finaled 12/19/2023 RUBEN SALAS

Permit Application Clearance Information

Clean Up Green Up Cleared 6/6/2023 STEVEN WECHSLER
Roof/Waste drainage to street Cleared 6/8/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 6/9/2023 FERNANDO GIL
Low Impact Development (LID) Cleared 9/28/2023 MELINEH AGHAKHABIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/12/2023 Corrections Issued WILLIAM WREN
Green Building Rough 10/12/2023 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Approved DAVID MATSON
Footing/Foundation/Slab 10/31/2023 Approved DAVID MATSON
BUILDING-Rough-Frame 11/20/2023 Corrections Issued CHRISTOPHER ROJAS
Final 11/20/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 11/20/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Rough 11/20/2023 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 11/20/2023 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 12/4/2023 Approved MATTHEW NELSON
Final 12/4/2023 OK to Issue CofO MATTHEW NELSON
Green Building Final 12/4/2023 Approved MATTHEW NELSON
Green Building Rough 12/4/2023 Approved MATTHEW NELSON
Smoke Detectors 12/4/2023 Approved MATTHEW NELSON