8457 N RINCON AVE 91352
Certificate Information: 8457 N RINCON AVE 91352
- Application / Permit
- 23014-20000-01894
- Plan Check / Job No.
- B23VN06316
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Patio addition to (E) single family dwellling
- Permit Issued
- Issued on 10/4/2023
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2023 | EDWIN ESPIN |
| Corrections Issued | 6/3/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 6/29/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/17/2023 | DANIEL SMILEY |
| Plan Check Approved | 10/1/2023 | SHANGQIN XIE |
| Issued | 10/4/2023 | APPLICANT |
| CofO in Progress | 12/6/2023 | MATTHEW NELSON |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 6/6/2023 | STEVEN WECHSLER |
| Roof/Waste drainage to street | Cleared | 6/8/2023 | FERNANDO GIL |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2023 | FERNANDO GIL |
| Low Impact Development (LID) | Cleared | 9/28/2023 | MELINEH AGHAKHABIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/12/2023 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 10/12/2023 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Approved | DAVID MATSON |
| Footing/Foundation/Slab | 10/31/2023 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 11/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 11/20/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 11/20/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Rough | 11/20/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/20/2023 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/20/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 12/4/2023 | Approved | MATTHEW NELSON |
| Final | 12/4/2023 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 12/4/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 12/4/2023 | Approved | MATTHEW NELSON |
| Smoke Detectors | 12/4/2023 | Approved | MATTHEW NELSON |