15201 W DORIAN ST 91342

Certificate Information: 15201 W DORIAN ST 91342

Application / Permit
23014-20000-01875
Plan Check / Job No.
B23VN06268
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
43'-7" X 15'-8" ADDITION TO (E) TWO STORY SFD WITH ROOF DECK ABOVE PORTION OF THE ADDITION.
Permit Issued
Issued on 5/3/2024
Issuing Office
Valley
Current Status
Issued on 5/3/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/17/2023 ARTIN ZARUKIAN
Corrections Issued 5/18/2023 ARTIN ZARUKIAN
Building Plans Picked Up 6/21/2023 APPLICANT
Applicant returned to address corrections 2/23/2024 KAMYAR EMAMI
Applicant returned to address corrections 4/9/2024 HAYATO TSUCHIYA
Applicant returned to address corrections 5/1/2024 ISIS ARGUETA
Plan Check Approved 5/3/2024 ISIS ARGUETA
Issued 5/3/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/8/2024 EDGAR ALCARAZ
Sewer availability Cleared 3/8/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 4/4/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 5/2/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Chen,, Yeshen Jason; Lic. No.: C40169 20601 ALDA CT      WALNUT, CA 91789

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/21/2024 Approved KEVIN BERBERYAN
Deputy Drilled-In Anchors 6/24/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 6/24/2024 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 6/25/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 7/12/2024 Corrections Issued KEVIN BERBERYAN
Green Building Rough 7/12/2024 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Rough 7/12/2024 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 9/17/2024 Conditional Approval KEVIN BERBERYAN
ELECTRICAL-Rough 9/17/2024 Approved KEVIN BERBERYAN
Green Building Rough 9/17/2024 Not Ready for Inspection KEVIN BERBERYAN
MERV13>=Rough 9/17/2024 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 9/25/2024 Approved KEVIN BERBERYAN
Green Building Rough 9/25/2024 Approved KEVIN BERBERYAN
HVAC-Rough 9/25/2024 Approved KEVIN BERBERYAN
MERV13>=Rough 9/25/2024 Approved KEVIN BERBERYAN
Insulation 9/26/2024 Approved KEVIN BERBERYAN
Drywall Nailing 10/1/2024 Approved KEVIN BERBERYAN
Sewer 10/16/2024 Approved KEVIN BERBERYAN
Shower Pan 10/16/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 10/23/2024 Approved KEVIN BERBERYAN