904 N BEVERLY GLEN BLVD 90077

Certificate Information: 904 N BEVERLY GLEN BLVD 90077

Application / Permit
23014-20000-01873
Plan Check / Job No.
B23VN06260
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 10'7" X 25'4" ATTACHED GARAGE INTO HABITABLE SPACE. (N) 10' X 18'5" ATTACHED GARAGE. REMODEL OF EXISTING SFD. WORK DONE PER ENGINEERING.
Permit Issued
Issued on 8/3/2023
Issuing Office
Valley
Current Status
Issued on 8/3/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/17/2023 RAMA DABADGE
Corrections Issued 5/22/2023 RAMA DABADGE
Building Plans Picked Up 6/5/2023 APPLICANT
Applicant returned to address corrections 7/6/2023 JESSE ARELLANO
Issued 8/3/2023 APPLICANT
Permit Expired-Status Void 1/11/2025 MICHAEL PELHAM
Re-Activate Permit 2/19/2025 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/25/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 7/26/2023 JASON NG
Grading Pre-Inspection Cleared 8/3/2023 MADISON ODELL

Contact Information

Contractor Owner-Builder       ,
Engineer Sayah,, Daniel H; Lic. No.: C67905 15233 VENTURA BLVD STE 1130      SHERMAN OAKS, CA 91403

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 1/11/2025 Not Ready for Inspection MICHAEL PELHAM
Deputy Drilled-In Anchors 2/20/2025 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 2/21/2025 Approved SEAN HAUPT
Footing/Foundation/Slab 2/21/2025 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Partial Approval SEAN HAUPT
Insulation 3/28/2025 Partial Approval SEAN HAUPT
PLUMBING-Rough 3/28/2025 Partial Approval SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Approved CARLOS MATAMOROS
Sewer 4/8/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 4/25/2025 Approved SEAN HAUPT
HVAC-Rough 4/25/2025 Approved SEAN HAUPT
BUILDING-Rough-Frame 5/8/2025 Conditional Approval STEPHANIE SWANSON
Green Building Rough 5/8/2025 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 5/8/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 5/8/2025 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 5/14/2025 Approved SEAN HAUPT
Drywall Nailing 5/14/2025 Partial Approval SEAN HAUPT
Green Building Rough 5/14/2025 Approved SEAN HAUPT
Insulation 5/14/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 5/14/2025 Approved SEAN HAUPT
PLUMBING-Rough 5/14/2025 Approved SEAN HAUPT
Drywall Nailing 5/20/2025 Approved SEAN HAUPT
Shower Pan 8/14/2025 Approved SEAN HAUPT
Interior/Exterior Lathing 8/21/2025 Approved SEAN HAUPT
HVAC-Rough 11/6/2025 Approved SEAN HAUPT
HVAC-Rough 1/26/2026 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 2/4/2026 Approved CARLOS MATAMOROS