11561 W LA MAIDA ST 91601

Certificate Information: 11561 W LA MAIDA ST 91601

Application / Permit
23014-20000-01869
Plan Check / Job No.
B23VN06250
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20' X 32' ONE STORY ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g) ALL WORK PER WFPP NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 4/15/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/31/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/31/2023 OMID HEDAYAT
Building Plans Picked Up 6/16/2023 APPLICANT
Applicant returned to address corrections 7/5/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/27/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/17/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 2/22/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/8/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/11/2024 SEWADA ZADOORAN MILAGARDI
Issued 4/15/2024 APPLICANT
Permit Finaled 7/8/2025 RUBEN SALAS
CofO Issued 7/8/2025 RUBEN SALAS
Permit Finaled 7/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/1/2023 LEE GUILBEAUX
Miscellaneous Cleared 8/4/2023 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 8/11/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/11/2023 DAGOVERTO GUERRERO
Specific Plan Cleared 11/8/2023 CHRISTIAN PEARSON
ZI Cleared 11/8/2023 CHRISTIAN PEARSON
ZI Cleared 11/8/2023 CHRISTIAN PEARSON
Construction near power lines Cleared 11/27/2023 RIDWAN HARDY
Construction within easement Cleared 11/27/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 2/5/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 2/6/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/5/2024 Not Ready for Inspection KEVIN BERBERYAN
Underground Mechanical 7/10/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/12/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/12/2024 Approved CHRISTOPHER ROJAS
Final 8/12/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 8/12/2024 Approved CHRISTOPHER ROJAS
Rough-Elec/Plmb/HVAC 8/12/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 8/12/2024 Approved CHRISTOPHER ROJAS
Insulation 8/16/2024 Corrections Issued CHRISTOPHER ROJAS
Shower Pan 8/16/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 8/30/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 8/30/2024 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/10/2024 Approved GAREN HAYRAPETYAN
Special/Order Compliance 9/18/2024 Partial Approval CHRISTOPHER ROJAS
ELECTRICAL-Final 4/28/2025 Partial Inspection JAVIER RAMOS JR
Final 4/28/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 4/28/2025 Approved JAVIER RAMOS JR
HVAC-Final 4/28/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 4/28/2025 Partial Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 4/28/2025 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 4/28/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Final 4/30/2025 Approved JAVIER RAMOS JR
Final 4/30/2025 Partial Inspection JAVIER RAMOS JR
PLUMBING-Final 4/30/2025 Approved JAVIER RAMOS JR
Final 6/6/2025 Conditional Approval JAVIER RAMOS JR
Service/Power Release 6/6/2025 Approved JAVIER RAMOS JR