11559 W LA MAIDA ST 91601

Certificate Information: 11559 W LA MAIDA ST 91601

Application / Permit
23014-20000-01868
Plan Check / Job No.
B23VN06250
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADD (N) 24' X 10'-8" TRELLIS ON FIRST FLOOR IN REAR, ENCLOSE 5' X4' SIDE PORCH, 4' X 6' PORTION OF (E) FRONT PORCH, (N) IRREGULAR SHAPED 53' X 43' SECOND FLOOR ADDITON TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 4/15/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 5/31/2023 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 5/31/2023 OMID HEDAYAT
Building Plans Picked Up 6/16/2023 APPLICANT
Applicant returned to address corrections 7/5/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 7/27/2023 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 1/17/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 2/22/2024 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 3/8/2024 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/11/2024 SEWADA ZADOORAN MILAGARDI
Issued 4/15/2024 APPLICANT
Permit Finaled 7/3/2025 RUBEN SALAS
CofO Issued 7/3/2025 RUBEN SALAS
Permit Finaled 7/3/2025 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 8/4/2023 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 8/11/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 8/11/2023 DAGOVERTO GUERRERO
Specific Plan Cleared 11/8/2023 CHRISTIAN PEARSON
ZI Cleared 11/8/2023 CHRISTIAN PEARSON
ZI Cleared 11/8/2023 CHRISTIAN PEARSON
Low Impact Development (LID) Cleared 2/5/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 2/6/2024 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/25/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/2/2024 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 7/5/2024 Partial Approval KEVIN BERBERYAN
Deputy Reinf. Concrete 7/9/2024 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 7/17/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 7/19/2024 Partial Approval CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/19/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Corrections Issued CHRISTOPHER ROJAS
Deputy Wood Construction 8/7/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 9/11/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/30/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/21/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 10/21/2024 Partial Inspection CHRISTOPHER ROJAS
HVAC-Rough 10/21/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 10/21/2024 Not Ready for Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/22/2024 Approved JENNIFER RABUCHIN
Green Building Rough 10/22/2024 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 10/25/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/1/2024 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 11/1/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 11/1/2024 Partial Inspection CHRISTOPHER ROJAS
PLUMBING-Rough 11/6/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/12/2024 Corrections Issued CHRISTOPHER ROJAS
Structural Steel Frame 11/12/2024 Approved CHRISTOPHER ROJAS
Insulation 11/20/2024 Approved CHRISTOPHER ROJAS
Shower Pan 11/20/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 12/2/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/16/2024 Partial Approval CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/24/2024 Approved RYAN SALAZAR
Sewer 1/17/2025 Partial Approval CHRISTOPHER ROJAS
Sewer 1/23/2025 Approved CHRISTOPHER ROJAS
Grounding or Bonding 3/20/2025 Partial Approval CHRISTOPHER ROJAS
Special/Order Compliance 3/20/2025 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 3/20/2025 Approved CHRISTOPHER ROJAS
Gas Test 4/10/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Final 4/28/2025 Approved JAVIER RAMOS JR
Final 4/28/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Final 4/28/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 4/28/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 4/28/2025 Partial Approval JAVIER RAMOS JR
Smoke Detectors 4/28/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/6/2025 Approved JAVIER RAMOS JR
Final 6/6/2025 Conditional Approval JAVIER RAMOS JR
Green Building Final 6/6/2025 Approved JAVIER RAMOS JR
Final 7/3/2025 Partial Approval JAVIER RAMOS JR