11559 W LA MAIDA ST 91601
Certificate Information: 11559 W LA MAIDA ST 91601
- Application / Permit
- 23014-20000-01868
- Plan Check / Job No.
- B23VN06250
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADD (N) 24' X 10'-8" TRELLIS ON FIRST FLOOR IN REAR, ENCLOSE 5' X4' SIDE PORCH, 4' X 6' PORTION OF (E) FRONT PORCH, (N) IRREGULAR SHAPED 53' X 43' SECOND FLOOR ADDITON TO (E) SINGLE FAMILY DWELLING ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT
- Permit Issued
- Issued on 4/15/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/31/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 5/31/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 6/16/2023 | APPLICANT |
| Applicant returned to address corrections | 7/5/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 7/27/2023 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 1/17/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 2/22/2024 | SEWADA ZADOORIAN MILAGARDI |
| Applicant returned to address corrections | 3/8/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/11/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/15/2024 | APPLICANT |
| Permit Finaled | 7/3/2025 | RUBEN SALAS |
| CofO Issued | 7/3/2025 | RUBEN SALAS |
| Permit Finaled | 7/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/4/2023 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 8/11/2023 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 11/8/2023 | CHRISTIAN PEARSON |
| ZI | Cleared | 11/8/2023 | CHRISTIAN PEARSON |
| ZI | Cleared | 11/8/2023 | CHRISTIAN PEARSON |
| Low Impact Development (LID) | Cleared | 2/5/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 2/6/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 7/5/2024 | Partial Approval | KEVIN BERBERYAN |
| Deputy Reinf. Concrete | 7/9/2024 | Conditional Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 7/17/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Insulation | 7/19/2024 | Partial Approval | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/19/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 8/7/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 9/11/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/30/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/21/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/21/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/21/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/21/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/22/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/22/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/25/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/1/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 11/1/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/1/2024 | Partial Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/6/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/12/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Structural Steel Frame | 11/12/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 11/20/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 11/20/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/2/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/16/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/24/2024 | Approved | RYAN SALAZAR |
| Sewer | 1/17/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Sewer | 1/23/2025 | Approved | CHRISTOPHER ROJAS |
| Grounding or Bonding | 3/20/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Special/Order Compliance | 3/20/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 3/20/2025 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 4/10/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 4/28/2025 | Approved | JAVIER RAMOS JR |
| Final | 4/28/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 4/28/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 4/28/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/28/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 4/28/2025 | Partial Approval | JAVIER RAMOS JR |
| Smoke Detectors | 4/28/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/6/2025 | Conditional Approval | JAVIER RAMOS JR |
| Green Building Final | 6/6/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/3/2025 | Partial Approval | JAVIER RAMOS JR |