10214 N WHITEGATE AVE 91040
Certificate Information: 10214 N WHITEGATE AVE 91040
- Application / Permit
- 23014-20000-01867
- Plan Check / Job No.
- B23VN06248
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition and convert (E) detached garage to ADU Per GCS 65852.2(e)(1)(B) and LAMC 12.22A33 (c)(d)&(g)
- Permit Issued
- Issued on 2/8/2024
- Issuing Office
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/17/2023 | ZAW HAN |
| Corrections Issued | 5/18/2023 | ZAW HAN |
| Applicant returned to address corrections | 12/7/2023 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 2/1/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 2/7/2024 | SHANGQIN XIE |
| Issued | 2/8/2024 | APPLICANT |
| CofO in Progress | 3/19/2025 | MATTHEW NELSON |
| Permit Finaled | 4/3/2025 | RUBEN SALAS |
| CofO Issued | 4/3/2025 | RUBEN SALAS |
| Permit Finaled | 4/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/20/2023 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 5/25/2023 | ROBERT HUGHES |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2023 | CARLOS AGUILERA |
| Private sewage disp. approval | Cleared | 11/28/2023 | VASIL MIHALEV |
| Watercourse | Cleared | 2/5/2024 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/30/2024 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 5/30/2024 | Corrections Issued | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 6/11/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 6/12/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2024 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/17/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 7/17/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/30/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/30/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/30/2024 | Approved | DAVID ANDERSON |
| Insulation | 8/6/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/6/2024 | Partial Approval | DAVID ANDERSON |
| Drywall Nailing | 8/15/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/15/2024 | Approved | DAVID ANDERSON |
| Shower Pan | 8/15/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 11/8/2024 | Approved | JACK KARGODORIAN |
| Service/Power Release | 11/20/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Service/Power Release | 1/23/2025 | Corrections Issued | DAVID ANDERSON |
| Final | 2/25/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 2/25/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 3/17/2025 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/17/2025 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 3/17/2025 | Approved | MATTHEW NELSON |