5078 N CERRILLOS DR 91364

Certificate Information: 5078 N CERRILLOS DR 91364

Application / Permit
23014-20000-01861
Plan Check / Job No.
B23VN06222
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW (16'-0"x24'-0"), 384 SQFT ADDITION TO AN EXISTING 2-CAR GARAGE ON A SLOPING LOT PER ENGINEERING DESIGN.
Permit Issued
Issued on 6/23/2023
Issuing Office
Current Status
CofO Issued on 2/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 PETER MOSESIAN
Corrections Issued 5/20/2023 PETER MOSESIAN
Quality Review Completed 5/23/2023 OMID HEDAYAT
Building Plans Picked Up 5/26/2023 APPLICANT
Plan Check Approved 6/23/2023 PETER MOSESIAN
Issued 6/23/2023 APPLICANT
CofO in Progress 8/2/2024 JOHN HAYES
Permit Finaled 2/19/2026 JOHN JANSON
CofO Issued 2/19/2026 JOHN JANSON
Permit Finaled 2/19/2026 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/5/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 6/5/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 6/5/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 6/5/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 6/5/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 6/5/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 6/5/2023 NIKKI ZULUETA
ZA Case Cleared 6/5/2023 ALEX VELA
Trees in Parkway Cleared 6/15/2023 ADALBERTO VERA
GPI Written Notices Cleared 6/23/2023 PETER MOSESIAN
Grading Pre-Inspection Cleared 6/23/2023 PETER MOSESIAN
Permit Cleared 6/23/2023 MARKOS PEREZ-BRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2023 Not Ready for Inspection SEAN HAUPT
Footing/Foundation/Slab 7/19/2023 Approved PETER FOLLING
Masonry Wall/Backfill 7/25/2023 Partial Approval PETER FOLLING
Masonry Wall/Backfill 7/28/2023 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 8/14/2023 Not Ready for Inspection PETER FOLLING
Green Building Rough 8/14/2023 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 8/31/2023 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 8/31/2023 Approved PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Approved PETER FOLLING
Green Building Rough 8/31/2023 Approved PETER FOLLING
Wood Frame 8/31/2023 Not Ready for Inspection PETER FOLLING
Interior/Exterior Lathing 9/6/2023 Approved PETER FOLLING
Drywall Nailing 9/18/2023 Approved PETER FOLLING
BUILDING-Rough-Frame 8/1/2024 Approved JOHN HAYES
Final 8/1/2024 OK to Issue CofO JOHN HAYES
Green Building Final 8/1/2024 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 8/1/2024 SGSOV Approved JOHN HAYES
Smoke Detectors 8/1/2024 Approved JOHN HAYES