6319 N CAMELLIA AVE 91606
Certificate Information: 6319 N CAMELLIA AVE 91606
- Application / Permit
- 23014-20000-01856
- Plan Check / Job No.
- B23VN06199
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERT DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2023 | ROSENDO MEDINA |
| Corrections Issued | 5/16/2023 | ROSENDO MEDINA |
| Applicant returned to address corrections | 8/17/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 8/29/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 8/31/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 9/6/2023 | ROSENDO MEDINA |
| Issued | 9/6/2023 | APPLICANT |
| CofO in Progress | 2/14/2024 | JENNIFER RABUCHIN |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
| CofO Issued | 4/3/2024 | RUBEN SALAS |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/12/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 8/10/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/15/2023 | JOHN LIN |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/12/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 9/18/2023 | Partial Approval | JOHN HAYES |
| Footing/Foundation/Slab | 9/25/2023 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 9/26/2023 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 10/20/2023 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Partial Approval | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 10/20/2023 | Corrections Issued | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/27/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/27/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 10/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 10/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 10/27/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 11/3/2023 | Approved | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 11/3/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 11/3/2023 | Approved | JOHN COLEMAN |
| Insulation | 11/13/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/13/2023 | Approved | JOHN HAYES |
| Underground Mechanical | 11/13/2023 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 11/16/2023 | Corrections Issued | JOSE AVILA |
| Drywall Nailing | 11/20/2023 | Approved | DAVID MATSON |
| ELECTRICAL-Final | 12/20/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/20/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/20/2023 | Approved | JOHN HAYES |
| HVAC-Final | 12/20/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 12/20/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/20/2023 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 12/20/2023 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 12/20/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 12/29/2023 | Corrections Issued | CRAIG DAVIS |
| Final | 12/29/2023 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 12/29/2023 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 12/29/2023 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/29/2023 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 12/29/2023 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Final | 1/18/2024 | No Access for Inspection | CRAIG DAVIS |
| Final | 1/18/2024 | No Access for Inspection | CRAIG DAVIS |
| PLUMBING-Final | 1/18/2024 | No Access for Inspection | CRAIG DAVIS |
| Service/Power Release | 1/18/2024 | No Access for Inspection | CRAIG DAVIS |
| ELECTRICAL-Final | 1/25/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/25/2024 | Corrections Issued | JOHN HAYES |
| PLUMBING-Final | 1/25/2024 | Not Ready for Inspection | JOHN HAYES |
| Service/Power Release | 1/25/2024 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 1/27/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/27/2024 | Off-Hour Fees Due | |
| PLUMBING-Final | 1/27/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 1/27/2024 | Off-Hour Fees Due | |
| Service/Power Release | 1/27/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 1/27/2024 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 2/8/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 2/8/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 2/8/2024 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/8/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 2/8/2024 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/13/2024 | Approved | JENNIFER RABUCHIN |
| Final | 2/13/2024 | OK to Issue CofO | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/13/2024 | Approved | JENNIFER RABUCHIN |