6534 N GOODLAND AVE 91606

Certificate Information: 6534 N GOODLAND AVE 91606

Application / Permit
23014-20000-01833
Plan Check / Job No.
B23VN06112
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 12' X 16' TO & CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 6/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 SELLA BENYAMIN
Corrections Issued 5/16/2023 SELLA BENYAMIN
Quality Review Completed 5/18/2023 STEVEN KIM
Building Plans Picked Up 5/19/2023 APPLICANT
Plan Check Approved 6/16/2023 SELLA BENYAMIN
Issued 6/16/2023 APPLICANT
CofO in Progress 5/8/2024 JOSE AVILA
Permit Finaled 5/10/2024 RUBEN SALAS
CofO Issued 5/10/2024 RUBEN SALAS
Permit Finaled 5/10/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 5/19/2023 WALTER RAMIREZ
Address approval Cleared 5/22/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 5/22/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/23/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/6/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/6/2023 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 9/12/2023 Approved KIRK SANDERS
Underground Mechanical 9/12/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Approved KIRK SANDERS
Sewer 10/23/2023 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 10/23/2023 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 10/27/2023 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 11/1/2023 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/1/2023 Corrections Issued CHRISTOPHER ROJAS
Green Building Rough 11/1/2023 Not Ready for Inspection CHRISTOPHER ROJAS
HVAC-Rough 11/1/2023 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 11/1/2023 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/13/2023 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Rough 11/13/2023 Approved JUAN VALENZUELA
Green Building Rough 11/13/2023 Approved JUAN VALENZUELA
HVAC-Rough 11/13/2023 Approved JUAN VALENZUELA
PLUMBING-Rough 11/13/2023 Approved JUAN VALENZUELA
Insulation 11/17/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 11/17/2023 Partial Approval KIRK SANDERS
Drywall Nailing 11/29/2023 Partial Approval KIRK SANDERS
Insulation 11/29/2023 Corrections Issued KIRK SANDERS
Interior/Exterior Lathing 11/29/2023 Approved KIRK SANDERS
Shower Pan 11/29/2023 Approved KIRK SANDERS
Underground Mechanical 12/5/2023 Corrections Issued JOSE AVILA
Final 4/1/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/1/2024 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/1/2024 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/1/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 4/5/2024 Approved JOSE AVILA
Final 4/5/2024 Corrections Issued JOSE AVILA
Final 4/12/2024 Corrections Issued JOSE AVILA
Final 4/29/2024 Not Ready for Inspection JOSE AVILA
Final 5/7/2024 OK to Issue CofO JOSE AVILA
Service/Power Release 5/8/2024 Approved JOSE AVILA