13355-13357 W DEBBY ST 91401
Certificate Information: 13355-13357 W DEBBY ST 91401
- Application / Permit
- 23014-20000-01826
- Plan Check / Job No.
- B23VN06094
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20' X 21'-11" ATTACHED GARAGE AND ADD 20' X 21'-11" TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- Current Status
- CofO Issued on 12/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | RAPHAEL ROSAS |
| Corrections Issued | 5/31/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 6/1/2023 | STEVEN KIM |
| Building Plans Picked Up | 6/2/2023 | APPLICANT |
| Applicant returned to address corrections | 6/15/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 6/20/2023 | RAPHAEL ROSAS |
| Issued | 6/20/2023 | APPLICANT |
| CofO in Progress | 10/13/2023 | KIRK SANDERS |
| No Progress | 12/1/2023 | RUBEN SALAS |
| CofO in Progress | 12/20/2023 | KIRK SANDERS |
| Permit Finaled | 12/20/2023 | RUBEN SALAS |
| CofO Issued | 12/20/2023 | RUBEN SALAS |
| Permit Finaled | 12/20/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 6/7/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/7/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Productive Home Renovation Inc; Lic. No.: 1076623-B | 12444 VICTORY BLVD #402 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/22/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/22/2023 | Corrections Issued | KIRK SANDERS |
| Deputy Drilled-In Anchors | 6/30/2023 | Approved | KIRK SANDERS |
| Footing/Foundation/Slab | 6/30/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 6/30/2023 | Approved | KIRK SANDERS |
| Deputy Wood Construction | 7/3/2023 | Conditional Approval | ROBERT GOLD |
| Wood Frame | 7/10/2023 | Corrections Issued | KIRK SANDERS |
| Deputy Wood Construction | 8/2/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 8/3/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 8/3/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 8/3/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 8/3/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 8/7/2023 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 8/10/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 8/15/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 8/15/2023 | Approved | KIRK SANDERS |
| Final | 9/29/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 9/29/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 9/29/2023 | Approved | KIRK SANDERS |
| Final | 10/5/2023 | Conditional Approval | KIRK SANDERS |
| Final | 10/12/2023 | OK to Issue CofO | KIRK SANDERS |