13355-13357 W DEBBY ST 91401

Certificate Information: 13355-13357 W DEBBY ST 91401

Application / Permit
23014-20000-01826
Plan Check / Job No.
B23VN06094
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' X 21'-11" ATTACHED GARAGE AND ADD 20' X 21'-11" TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/20/2023
Issuing Office
Current Status
CofO Issued on 12/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 RAPHAEL ROSAS
Corrections Issued 5/31/2023 RAPHAEL ROSAS
Quality Review Completed 6/1/2023 STEVEN KIM
Building Plans Picked Up 6/2/2023 APPLICANT
Applicant returned to address corrections 6/15/2023 RAPHAEL ROSAS
Plan Check Approved 6/20/2023 RAPHAEL ROSAS
Issued 6/20/2023 APPLICANT
CofO in Progress 10/13/2023 KIRK SANDERS
No Progress 12/1/2023 RUBEN SALAS
CofO in Progress 12/20/2023 KIRK SANDERS
Permit Finaled 12/20/2023 RUBEN SALAS
CofO Issued 12/20/2023 RUBEN SALAS
Permit Finaled 12/20/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/7/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 6/7/2023 NIKKI ZULUETA
Roof/Waste drainage to street Cleared 6/7/2023 NIKKI ZULUETA
Sewer availability Cleared 6/7/2023 NIKKI ZULUETA

Contact Information

Contractor Productive Home Renovation Inc; Lic. No.: 1076623-B 12444 VICTORY BLVD #402      NORTH HOLLYWOOD, CA 91606
Engineer Rahman,, Moksudur; Lic. No.: C69263 14616 MCKENDREE AVE      CHINO, CA 91708

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/22/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/22/2023 Corrections Issued KIRK SANDERS
Deputy Drilled-In Anchors 6/30/2023 Approved KIRK SANDERS
Footing/Foundation/Slab 6/30/2023 Approved KIRK SANDERS
Underground Mechanical 6/30/2023 Approved KIRK SANDERS
Deputy Wood Construction 7/3/2023 Conditional Approval ROBERT GOLD
Wood Frame 7/10/2023 Corrections Issued KIRK SANDERS
Deputy Wood Construction 8/2/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/3/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 8/3/2023 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/3/2023 Approved KIRK SANDERS
Green Building Rough 8/3/2023 Approved KIRK SANDERS
HVAC-Rough 8/3/2023 Approved KIRK SANDERS
PLUMBING-Rough 8/3/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 8/7/2023 Partial Approval MISAEL ESPARZA
Shower Pan 8/10/2023 Approved KIRK SANDERS
Drywall Nailing 8/15/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 8/15/2023 Approved KIRK SANDERS
Final 9/29/2023 Corrections Issued KIRK SANDERS
Green Building Final 9/29/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/29/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 9/29/2023 Approved KIRK SANDERS
Final 10/5/2023 Conditional Approval KIRK SANDERS
Final 10/12/2023 OK to Issue CofO KIRK SANDERS