5740 N VESPER AVE 91411
Certificate Information: 5740 N VESPER AVE 91411
- Application / Permit
- 23014-20000-01825
- Plan Check / Job No.
- B23VN06089
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 9'-5" X 15'-8" ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 5/16/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/17/2023 | APPLICANT |
| Applicant returned to address corrections | 9/7/2023 | DANIEL ABRAMYAN |
| Issued | 9/8/2023 | APPLICANT |
| CofO in Progress | 3/18/2024 | RYAN SALAZAR |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
| CofO Issued | 4/1/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/1/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2023 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 5/19/2023 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2023 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 5/20/2023 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 8/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Zig Zag Construction Inc; Lic. No.: 1061320-B | 18653 VENTURA BLVD #393 TARZANA, CA 91356 |
| Engineer | Mourad,, Daniel; Lic. No.: C83387 | 542 N FULLER AVE LOS ANGELES, CA 90036 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/27/2023 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 12/4/2023 | Approved | RYAN SALAZAR |
| Sewer | 12/14/2023 | Approved | JOHN COLEMAN |
| Underground Mechanical | 12/14/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Rough | 1/5/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/5/2024 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 1/5/2024 | Approved | RYAN SALAZAR |
| Wood Frame | 1/5/2024 | Partial Approval | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Partial Approval | RYAN SALAZAR |
| HVAC-Rough | 1/9/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 1/9/2024 | Approved | RYAN SALAZAR |
| Wood Frame | 1/9/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2024 | Approved | RYAN SALAZAR |
| Insulation | 1/16/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/16/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 1/22/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/15/2024 | Approved | RYAN SALAZAR |
| Final | 3/15/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 3/15/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 3/15/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 3/15/2024 | Approved | RYAN SALAZAR |
| Smoke Detectors | 3/15/2024 | Approved | RYAN SALAZAR |