5740 N VESPER AVE 91411

Certificate Information: 5740 N VESPER AVE 91411

Application / Permit
23014-20000-01825
Plan Check / Job No.
B23VN06089
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
9'-5" X 15'-8" ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/8/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2023 APPLICANT
Assigned to Plan Check Engineer 5/15/2023 JEROME MAGAT PALMA
Corrections Issued 5/16/2023 JEROME MAGAT PALMA
Building Plans Picked Up 5/17/2023 APPLICANT
Applicant returned to address corrections 9/7/2023 DANIEL ABRAMYAN
Issued 9/8/2023 APPLICANT
CofO in Progress 3/18/2024 RYAN SALAZAR
Permit Finaled 4/1/2024 DANIEL ORRANTE
CofO Issued 4/1/2024 DANIEL ORRANTE
Permit Finaled 4/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/19/2023 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 5/19/2023 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 5/20/2023 MARKOS PEREZ-BRAN
Sewer availability Cleared 5/20/2023 MARKOS PEREZ-BRAN
Construction near power lines Cleared 8/21/2023 RIDWAN HARDY

Contact Information

Contractor Zig Zag Construction Inc; Lic. No.: 1061320-B 18653 VENTURA BLVD #393      TARZANA, CA 91356
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/27/2023 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 12/4/2023 Approved RYAN SALAZAR
Sewer 12/14/2023 Approved JOHN COLEMAN
Underground Mechanical 12/14/2023 Approved JOHN COLEMAN
ELECTRICAL-Rough 1/5/2024 Approved RYAN SALAZAR
HVAC-Rough 1/5/2024 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 1/5/2024 Approved RYAN SALAZAR
Wood Frame 1/5/2024 Partial Approval RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Partial Approval RYAN SALAZAR
HVAC-Rough 1/9/2024 Approved RYAN SALAZAR
Shower Pan 1/9/2024 Approved RYAN SALAZAR
Wood Frame 1/9/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Approved RYAN SALAZAR
Insulation 1/16/2024 Approved RYAN SALAZAR
Interior/Exterior Lathing 1/16/2024 Approved RYAN SALAZAR
Drywall Nailing 1/22/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 3/15/2024 Approved RYAN SALAZAR
Final 3/15/2024 OK to Issue CofO RYAN SALAZAR
Green Building Final 3/15/2024 Approved RYAN SALAZAR
Green Building Rough 3/15/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 3/15/2024 SGSOV Approved RYAN SALAZAR
Service/Power Release 3/15/2024 Approved RYAN SALAZAR
Smoke Detectors 3/15/2024 Approved RYAN SALAZAR