4929 N DENNY AVE 91601

Certificate Information: 4929 N DENNY AVE 91601

Application / Permit
23014-20000-01815
Plan Check / Job No.
B23VN06052
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 1 story addition at the rear of the property to include an enlarged M Bedroom and Kitchen and new bathroom.
Permit Issued
Issued on 6/11/2024
Issuing Office
Current Status
Issued on 6/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/11/2023 APPLICANT
Assigned to Plan Check Engineer 5/15/2023 KHUONG TRUONG
Corrections Issued 5/16/2023 KHUONG TRUONG
Applicant returned to address corrections 6/4/2024 ZAW HAN
Plan Check Approved 6/6/2024 ZAW HAN
Issued 6/11/2024 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 8/18/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 4/26/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/26/2024 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 4/29/2024 CARLOS AGUILERA

Contact Information

Architect Diradourian,, Richard C; Lic. No.: C10336 2618 HERMOSA AVENUE      MONTROSE, CA 91020
Architect Diradourian,, Richard C; Lic. No.: NA10336       ,
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/3/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 6/23/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Deputy Drilled-In Anchors 9/5/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/9/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/16/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 9/17/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 12/10/2025 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/18/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 12/18/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/3/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 3/3/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 3/3/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 3/3/2026 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/17/2026 Approved GAREN HAYRAPETYAN
Insulation 3/17/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 3/17/2026 Approved GAREN HAYRAPETYAN
Shower Pan 3/17/2026 Approved GAREN HAYRAPETYAN
Drywall Nailing 3/24/2026 Approved RAUL OLAGI