10849 N VENA AVE 91345

Certificate Information: 10849 N VENA AVE 91345

Application / Permit
23014-20000-01800
Plan Check / Job No.
B23VN06026
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 16'-9" X 34'-5" IRREGULAR SHAPED 2-STORY TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/31/2023
Issuing Office
Current Status
CofO Issued on 10/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 RAPHAEL ROSAS
Corrections Issued 6/7/2023 RAPHAEL ROSAS
Quality Review Completed 6/16/2023 STEVEN KIM
Applicant returned to address corrections 9/27/2023 RAPHAEL ROSAS
Plan Check Approved 10/5/2023 RAPHAEL ROSAS
Issued 10/31/2023 APPLICANT
CofO in Progress 8/27/2024 JENNIFER RABUCHIN
CofO Issued 10/3/2024 DANIEL ORRANTE
Permit Finaled 10/3/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/23/2023 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 8/24/2023 FERNANDO GIL
Sewer availability Cleared 8/24/2023 FERNANDO GIL
Construction near power lines Cleared 9/6/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 9/15/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 9/19/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/22/2023 Corrections Issued JENNIFER RABUCHIN
Deputy Drilled-In Anchors 11/29/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 12/1/2023 Partial Approval JENNIFER RABUCHIN
METHANE-Barrier 12/1/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 12/1/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 12/1/2023 Partial Approval JENNIFER RABUCHIN
Sewer 12/1/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/11/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 12/11/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 12/11/2023 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 12/11/2023 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 12/11/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/19/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 12/19/2023 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 1/2/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 1/2/2024 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 1/2/2024 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 1/2/2024 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/26/2024 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 2/26/2024 Approved MATTHEW NELSON
HVAC-Rough 2/26/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/26/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 2/26/2024 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 3/6/2024 No Access for Inspection WILLIAM WREN
ELECTRICAL-Rough 3/6/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 3/6/2024 Approved WILLIAM WREN
MERV13>=Rough 3/6/2024 Approved WILLIAM WREN
PLUMBING-Rough 3/6/2024 Approved WILLIAM WREN
Insulation 3/13/2024 Corrections Issued JENNIFER RABUCHIN
Shower Pan 3/13/2024 Corrections Issued JENNIFER RABUCHIN
Insulation 3/15/2024 Approved JENNIFER RABUCHIN
Shower Pan 3/15/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 3/20/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 3/20/2024 Approved JENNIFER RABUCHIN
Gas Test 6/7/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/21/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/21/2024 Corrections Issued JENNIFER RABUCHIN
Final 6/21/2024 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 6/21/2024 Approved JENNIFER RABUCHIN
Green Building Final 6/21/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 6/21/2024 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 6/21/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/21/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 6/21/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/27/2024 Approved JENNIFER RABUCHIN
Final 8/27/2024 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 8/27/2024 Approved JENNIFER RABUCHIN
HVAC-Final 8/27/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/27/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/27/2024 SGSOV Approved JENNIFER RABUCHIN