4427 N MORELLA AVE 1 91607
Certificate Information: 4427 N MORELLA AVE 1 91607
- Application / Permit
- 23014-20000-01784
- Plan Check / Job No.
- B23VN05985
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePLAN. 15' X 13'6" ADDITION AND INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING PER ENGINEER
- Permit Issued
- Issued on 5/26/2023
- Issuing Office
- Current Status
- CofO Issued on 7/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2023 | PINANK PATEL |
| Corrections Issued | 5/10/2023 | PINANK PATEL |
| Plan Check Approved | 5/23/2023 | LUISANGEL VALENZUELA |
| Issued | 5/26/2023 | APPLICANT |
| CofO in Progress | 9/21/2023 | JACK KARGODORIAN |
| Permit Finaled | 7/2/2024 | RUBEN SALAS |
| CofO Issued | 7/2/2024 | RUBEN SALAS |
| Permit Finaled | 7/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 5/15/2023 | DALIA MOKAYED |
| Roof/Waste drainage to street | Cleared | 5/16/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/16/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | New Beginning Construction Company Corp The; Lic. No.: 848904-B | , |
| Contractor | New Beginnning Construction Company The; Lic. No.: 848904-B | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: NA91046 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/6/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 6/8/2023 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Partial Approval | JACK KARGODORIAN |
| Insulation | 6/13/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 6/28/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 7/18/2023 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 7/18/2023 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 7/18/2023 | Corrections Issued | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 7/26/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 7/26/2023 | Approved | JUAN VALENZUELA |
| Insulation | 7/26/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/26/2023 | Partial Approval | JUAN VALENZUELA |
| Drywall Nailing | 8/1/2023 | Approved | JACK KARGODORIAN |
| Final | 9/20/2023 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 9/20/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 9/20/2023 | Approved | JACK KARGODORIAN |