13280-13282 W JUDD ST 91331

Certificate Information: 13280-13282 W JUDD ST 91331

Application / Permit
23014-20000-01776
Plan Check / Job No.
B23VN05938
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT PORTION OF (E) SFD WITH THE ATTACHED PATIO COVER TO ATTACHED SECOND UNIT SFD PER SB9 AND ADD ATTACHED CARPORT.
Permit Issued
Issued on 5/26/2023
Issuing Office
Valley
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 JESSE ARELLANO
Corrections Issued 5/13/2023 JESSE ARELLANO
Building Plans Picked Up 5/17/2023 APPLICANT
Issued 5/26/2023 APPLICANT
CofO in Progress 4/19/2024 MICHEL ABAJAN
Permit Finaled 5/1/2024 RUBEN SALAS
CofO Issued 5/1/2024 RUBEN SALAS
Permit Finaled 5/1/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/18/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 5/18/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/19/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 5/19/2023 DAGOVERTO GUERRERO
Senate Bill 9 Cleared 5/26/2023 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/20/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/22/2023 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 9/22/2023 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 10/12/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 10/12/2023 Approved MICHEL ABAJAN
Footing/Foundation/Slab 10/12/2023 Approved MICHEL ABAJAN
Green Building Rough 10/12/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 10/12/2023 Approved MICHEL ABAJAN
Wood Frame 10/12/2023 Approved MICHEL ABAJAN
Drywall Nailing 12/14/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/14/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/12/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 2/12/2024 Approved MICHEL ABAJAN
Final 2/12/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 2/12/2024 Approved MICHEL ABAJAN
HVAC-Final 2/12/2024 Approved MICHEL ABAJAN
PLUMBING-Final 2/12/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 2/12/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 2/12/2024 Approved MICHEL ABAJAN
Final 2/21/2024 OK to Issue CofO MICHEL ABAJAN