10826 N YARMOUTH AVE 91344
Certificate Information: 10826 N YARMOUTH AVE 91344
- Application / Permit
- 23014-20000-01770
- Plan Check / Job No.
- B23VN05913
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN Addition to (E) 1-story sfd and attached garage and remodel. Alter (E) roof above (E) garage, change of door
- Permit Issued
- Issued on 6/29/2023
- Issuing Office
- Current Status
- CofO Issued on 12/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2023 | MINA HABILI |
| Corrections Issued | 5/10/2023 | MINA HABILI |
| Applicant returned to address corrections | 6/21/2023 | DANIEL SMILEY |
| Plan Check Approved | 6/29/2023 | JOSEPH RAFOLS |
| Issued | 6/29/2023 | APPLICANT |
| CofO in Progress | 11/21/2023 | STEVEN BACK |
| CofO in Progress | 11/21/2023 | STEVEN BACK |
| CofO in Progress | 12/4/2023 | STEVEN BACK |
| Permit Finaled | 12/13/2023 | JOHN JANSON |
| CofO Issued | 12/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/9/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Dhe Best Construction Inc; Lic. No.: 1051288-B | , |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/12/2023 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/13/2023 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/19/2023 | Partial Approval | STEVEN BACK |
| Green Building Rough | 7/19/2023 | Not Ready for Inspection | STEVEN BACK |
| Insulation | 7/19/2023 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 7/19/2023 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 8/11/2023 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/11/2023 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 8/11/2023 | Approved | STEVEN BACK |
| PLUMBING-Rough | 8/11/2023 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 8/15/2023 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2023 | Approved | STEVEN BACK |
| Green Building Rough | 8/15/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/15/2023 | Partial Approval | STEVEN BACK |
| Insulation | 8/17/2023 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 8/21/2023 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/21/2023 | Approved | STEVEN BACK |
| Final | 11/21/2023 | Partial Approval | STEVEN BACK |
| Green Building Final | 11/21/2023 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 11/21/2023 | Approved | STEVEN BACK |
| Final | 11/22/2023 | Corrections Issued | STEVEN BACK |
| Final | 12/4/2023 | OK to Issue CofO | STEVEN BACK |