3142 S BUTLER AVE 90066
Certificate Information: 3142 S BUTLER AVE 90066
- Application / Permit
- 23014-20000-01762
- Plan Check / Job No.
- B23VN05888
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 14'-0" X 13'-0" & 14'-0" X 10'-7" ADDITION TO & CONVERT (E) 18'-0" X 20'-0" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 8/3/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 5/12/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/15/2023 | APPLICANT |
| Plan Check Approved | 8/3/2023 | ISIS ARGUETA |
| Issued | 8/3/2023 | APPLICANT |
| CofO in Progress | 5/30/2024 | JESUS PINEDA |
| Permit Finaled | 5/31/2024 | DANIEL ORRANTE |
| CofO Issued | 5/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/5/2023 | ALESSANDRO MERCURI |
| Address approval | Cleared | 6/6/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2023 | JASON NG |
| Sewer availability | Cleared | 6/7/2023 | JASON NG |
| Grading Pre-Inspection | Cleared | 6/8/2023 | SERGIO VALENZUELA |
| Construction near power lines | Cleared | 8/1/2023 | TINA MIRANDA |
| Roof/Waste drainage to street | Cleared | 8/1/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | 7110 FOREST HILLS RD WEST HILLS, CA 91307 |
| Engineer | Sin,, John Paul; Lic. No.: C91162 | 122 N GRAMERCY PL LOS ANGELES, CA 90004 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/21/2023 | Partial Approval | JESUS PINEDA |
| Sewer | 9/26/2023 | Approved | JESUS PINEDA |
| Excavation/Setback/Form/Re-Bar | 10/10/2023 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 10/10/2023 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/27/2023 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 11/27/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 11/27/2023 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 11/27/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 11/27/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 11/30/2023 | Corrections Issued | KENNETH NAGLE |
| BUILDING-Rough-Frame | 12/7/2023 | Approved | KENNETH NAGLE |
| Green Building Rough | 12/7/2023 | Approved | KENNETH NAGLE |
| PLUMBING-Rough | 12/7/2023 | Approved | KENNETH NAGLE |
| HVAC-Rough | 12/12/2023 | Approved | JESUS PINEDA |
| Insulation | 12/12/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 12/14/2023 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 12/27/2023 | Approved | KENNETH NAGLE |
| Service/Power Release | 12/27/2023 | Approved | KENNETH NAGLE |
| Shower Pan | 12/27/2023 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 12/29/2023 | Approved | JESUS PINEDA |
| Service/Power Release | 1/5/2024 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 5/9/2024 | Approved | JESUS PINEDA |
| Final | 5/9/2024 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 5/9/2024 | Approved | JESUS PINEDA |
| HVAC-Final | 5/9/2024 | Approved | JESUS PINEDA |
| PLUMBING-Final | 5/9/2024 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Not Ready | JESUS PINEDA |
| Smoke Detectors | 5/9/2024 | Approved | JESUS PINEDA |
| Final | 5/15/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/15/2024 | SGSOV Not Ready | CARLOS MATAMOROS |
| Final | 5/30/2024 | OK to Issue CofO | JESUS PINEDA |
| PLUMBING-Final | 5/30/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 5/30/2024 | SGSOV Approved | JESUS PINEDA |