5120 N MORELLA AVE 91607
Certificate Information: 5120 N MORELLA AVE 91607
- Application / Permit
- 23014-20000-01743
- Plan Check / Job No.
- B23VN05815
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 15'-10" X 16'-10" ADDITION TO & CONVERT (E) 18'-0" X 18'-0" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d),
- Permit Issued
- Issued on 11/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 5/9/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/10/2023 | APPLICANT |
| Applicant returned to address corrections | 9/21/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 11/7/2023 | HAYATO TSUCHIYA |
| Issued | 11/7/2023 | APPLICANT |
| CofO in Progress | 8/28/2024 | JUAN VALENZUELA |
| Permit Finaled | 8/31/2024 | DANIEL ORRANTE |
| CofO Issued | 8/31/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/31/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/23/2023 | CARLOS AGUILERA |
| Specific Plan | Cleared | 5/25/2023 | CHRISTIAN PEARSON |
| ZI | Cleared | 5/25/2023 | CHRISTIAN PEARSON |
| ZI | Cleared | 5/25/2023 | CHRISTIAN PEARSON |
| Construction near power lines | Cleared | 9/9/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/25/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/30/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 12/5/2023 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 12/11/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 12/14/2023 | Approved | KIRK SANDERS |
| Special/Order Compliance | 12/21/2023 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 12/26/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 1/16/2024 | Approved | KIRK SANDERS |
| Underground Mechanical | 1/16/2024 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/7/2024 | No Access for Inspection | KIRK SANDERS |
| Green Building Rough | 2/7/2024 | No Access for Inspection | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 2/7/2024 | No Access for Inspection | KIRK SANDERS |
| Rough-Elec/Plmb/HVAC | 2/8/2024 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 2/15/2024 | Not Ready for Inspection | ROBERT GOLD |
| ELECTRICAL-Rough | 2/15/2024 | Not Ready for Inspection | ROBERT GOLD |
| Green Building Rough | 2/15/2024 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Rough | 2/15/2024 | Not Ready for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/27/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 2/27/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Rough | 2/27/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Rough | 2/27/2024 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/1/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 3/1/2024 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 3/1/2024 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/5/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/5/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 3/5/2024 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/7/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 3/7/2024 | Approved | KIRK SANDERS |
| Wood Frame | 3/7/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 3/14/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 3/14/2024 | Approved | DAVID ANDERSON |
| Insulation | 3/19/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/26/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 3/26/2024 | Approved | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 3/26/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 3/26/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 7/25/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/25/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/25/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/25/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 8/12/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 8/12/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/12/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Final | 8/15/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 8/15/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Pre-Inspection | 8/22/2024 | Partial Inspection | JUAN VALENZUELA |
| Final | 8/28/2024 | OK to Issue CofO | JUAN VALENZUELA |