4200 N NAVAJO ST 91602
Certificate Information: 4200 N NAVAJO ST 91602
- Application / Permit
- 23014-20000-01721
- Plan Check / Job No.
- B23VN05716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, (N) 13'-7" X 26'-11" ADDITION TO FIRST FLOOR, ADD HALF BATHROOM TO (E) RECROOM, PROVIDE STAIR ACCESS TO (E) 2ND FLOOR OF (E) SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE AND RECROOM ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 8/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 5/8/2023 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 5/8/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 5/9/2023 | APPLICANT |
| Plan Check Approved | 8/16/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 8/16/2023 | APPLICANT |
| CofO in Progress | 10/17/2024 | CHRISTOPHER ROJAS |
| CofO Issued | 10/22/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/22/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/23/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/23/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2023 | CARLOS AGUILERA |
| ZI | Cleared | 6/27/2023 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 7/18/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/8/2023 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/8/2023 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/15/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/9/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 11/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 1/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 1/22/2024 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 1/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Wood Construction | 1/25/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/21/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 2/21/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 2/21/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 3/5/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 3/5/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 3/12/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 3/14/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/15/2024 | Corrections Issued | JUAN VALENZUELA |
| Interior/Exterior Lathing | 3/15/2024 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 3/20/2024 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/21/2024 | Conditional Approval | KIRK SANDERS |
| Green Building Rough | 3/21/2024 | Approved | KIRK SANDERS |
| Insulation | 3/21/2024 | Approved | KIRK SANDERS |
| Drywall Nailing | 4/8/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/8/2024 | Partial Approval | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/11/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 10/1/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Final | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 10/4/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 10/4/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |
| HVAC-Final | 10/4/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Final | 10/4/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Approved | CHRISTOPHER ROJAS |