19749 W CANTLAY ST #1 - 3 91306
Certificate Information: 19749 W CANTLAY ST #1 - 3 91306
- Application / Permit
- 23014-20000-01711
- Plan Check / Job No.
- B23VN05668
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) 20'-2" X 19'-7"' ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 AND ADD 19'-7" X 28'-7" 2ND FLOOR FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/15/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | RAPHAEL ROSAS |
| Corrections Issued | 5/18/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 5/18/2023 | STEVEN KIM |
| Building Plans Picked Up | 6/9/2023 | APPLICANT |
| Applicant returned to address corrections | 6/26/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 6/28/2024 | RAPHAEL ROSAS |
| Issued | 7/2/2024 | APPLICANT |
| CofO in Progress | 3/11/2026 | ALEXANDER HANDY |
| Permit Finaled | 4/15/2026 | JOHN JANSON |
| CofO Issued | 4/15/2026 | JOHN JANSON |
| Permit Finaled | 4/15/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/13/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 10/27/2023 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 3/5/2024 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | JOHN LIN |
| Miscellaneous | Cleared | 3/29/2024 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/25/2024 | Conditional Approval | HENRY KIM |
| Excavation/Setback/Form/Re-Bar | 11/25/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 12/24/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 12/24/2024 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2025 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 2/21/2025 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 2/21/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 2/21/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 2/21/2025 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 2/21/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 3/11/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 3/11/2025 | Approved | JUAN ALVARADO |
| Insulation | 3/11/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 3/11/2025 | Approved | JUAN ALVARADO |
| Drywall Nailing | 3/17/2025 | Approved | GEVORK IPCHYAN |
| ELECTRICAL-Final | 1/30/2026 | Approved | ALEXANDER HANDY |
| Final | 1/30/2026 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 1/30/2026 | Approved | ALEXANDER HANDY |
| Green Building Final | 1/30/2026 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Final | 1/30/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/30/2026 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 1/30/2026 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/10/2026 | Approved | ALEXANDER HANDY |
| Final | 3/10/2026 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 3/10/2026 | Approved | ALEXANDER HANDY |
| HVAC-Final | 3/10/2026 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/10/2026 | Approved | ALEXANDER HANDY |