234 S WESTGATE AVE 90049
Certificate Information: 234 S WESTGATE AVE 90049
- Application / Permit
- 23014-20000-01680
- Plan Check / Job No.
- B23VN05543
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16'-2" x 8'-7"ADDITION TO (E) SFD AND REMODEL TO (E) SFD. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Current Status
- CofO Issued on 12/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 5/5/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/8/2023 | APPLICANT |
| Applicant returned to address corrections | 6/30/2023 | ISIS ARGUETA |
| Plan Check Approved | 7/7/2023 | MIROOSH KHACHATOORIAN |
| Issued | 7/7/2023 | APPLICANT |
| CofO in Progress | 12/21/2024 | MICHAEL PELHAM |
| Permit Finaled | 12/26/2024 | RICHARD STEINBACH |
| CofO Issued | 12/26/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/26/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/10/2023 | DARIN LAM |
| Miscellaneous | Cleared | 5/11/2023 | MAXFIELD VERMY |
| Grading Pre-Inspection | Cleared | 6/5/2023 | SERGIO VALENZUELA |
| Specific Plan | Cleared | 6/7/2023 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2023 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 6/26/2023 | ANTHONY MAINEZ |
Contact Information
| Contractor | Oag; Lic. No.: 1101018-B | 9712 LIVE OAK AVE TEMPLE CITY, CA 91780 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/4/2023 | Partial Approval | CARLOS MATAMOROS |
| Underground Mechanical | 8/4/2023 | Approved | CARLOS MATAMOROS |
| Deputy Drilled-In Anchors | 8/8/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 8/9/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 8/21/2023 | Partial Approval | CARLOS MATAMOROS |
| Shower Pan | 8/21/2023 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 8/29/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/29/2023 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 2/22/2024 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Conditional Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/19/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 4/19/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/29/2024 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/29/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 5/3/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/3/2024 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 5/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 5/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 5/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Shower Pan | 5/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 5/10/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/14/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/15/2024 | Corrections Issued | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 5/17/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 5/17/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/17/2024 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/20/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 5/20/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 5/20/2024 | Approved | CARLOS MATAMOROS |
| Wood Frame | 5/20/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 5/24/2024 | Corrections Issued | ARAM AVEDISIAN |
| Insulation | 5/31/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 6/4/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 6/4/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | CARLOS MATAMOROS |
| Final | 10/15/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 10/15/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 10/15/2024 | Corrections Issued | CARLOS MATAMOROS |
| Final | 11/25/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| Smoke Detectors | 11/25/2024 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 11/26/2024 | Approved | CARLOS MATAMOROS |