8220 N AMESTOY AVE 91325
Certificate Information: 8220 N AMESTOY AVE 91325
- Application / Permit
- 23014-20000-01611
- Plan Check / Job No.
- B23VN05313
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: 2-STORY ACCESSORY DWELING UNIT ADDITION TO (E) GARAGE PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 1/8/2024
- Issuing Office
- Current Status
- CofO Issued on 8/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | DANIEL YIP |
| Corrections Issued | 7/6/2023 | DANIEL YIP |
| Quality Review Completed | 7/6/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/20/2023 | DANIEL YIP |
| Plan Check Approved | 1/2/2024 | DANIEL YIP |
| Issued | 1/8/2024 | APPLICANT |
| CofO in Progress | 6/5/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
| CofO Issued | 8/28/2025 | RUBEN SALAS |
| Permit Finaled | 8/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/19/2023 | RYAN KIM |
| Sewer availability | Cleared | 7/21/2023 | RYAN KIM |
| Construction near power lines | Cleared | 10/11/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/11/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 11/13/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2023 | ROSE MARIE SMITH |
| Low Impact Development (LID) | Cleared | 12/12/2023 | ROGELIO CORTES |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/14/2024 | No Access for Inspection | RAUL OLAGI |
| Sewer | 2/14/2024 | No Access for Inspection | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 2/16/2024 | Partial Approval | RAUL OLAGI |
| Sewer | 2/16/2024 | Approved | RAUL OLAGI |
| Underground Mechanical | 2/16/2024 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 2/23/2024 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 2/28/2024 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 3/4/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Partial Inspection | RAUL OLAGI |
| Special/Order Compliance | 3/19/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 5/8/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 5/8/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/8/2024 | Partial Approval | RAUL OLAGI |
| Rough-Elec/Plmb/HVAC | 5/8/2024 | Approved | RAUL OLAGI |
| Shower Pan | 5/8/2024 | Approved | RAUL OLAGI |
| Insulation | 5/20/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/20/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 5/29/2024 | Approved | SALVADOR MARTINEZ |
| Final | 3/19/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 3/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Final | 3/19/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/19/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 3/25/2025 | Partial Inspection | GAREN HAYRAPETYAN |
| Green Building Final | 3/25/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 4/4/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| PLUMBING-Final | 4/4/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 4/4/2025 | Approved | SALVADOR MARTINEZ |