8220 N AMESTOY AVE 91325

Certificate Information: 8220 N AMESTOY AVE 91325

Application / Permit
23014-20000-01611
Plan Check / Job No.
B23VN05313
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: 2-STORY ACCESSORY DWELING UNIT ADDITION TO (E) GARAGE PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 1/8/2024
Issuing Office
Current Status
CofO Issued on 8/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 DANIEL YIP
Corrections Issued 7/6/2023 DANIEL YIP
Quality Review Completed 7/6/2023 GARO TELMI
Applicant returned to address corrections 11/20/2023 DANIEL YIP
Plan Check Approved 1/2/2024 DANIEL YIP
Issued 1/8/2024 APPLICANT
CofO in Progress 6/5/2025 SALVADOR MARTINEZ
Permit Finaled 8/28/2025 RUBEN SALAS
CofO Issued 8/28/2025 RUBEN SALAS
Permit Finaled 8/28/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/19/2023 RYAN KIM
Sewer availability Cleared 7/21/2023 RYAN KIM
Construction near power lines Cleared 10/11/2023 RIDWAN HARDY
Construction within easement Cleared 10/11/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 11/13/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 11/27/2023 ROSE MARIE SMITH
Low Impact Development (LID) Cleared 12/12/2023 ROGELIO CORTES

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/14/2024 No Access for Inspection RAUL OLAGI
Sewer 2/14/2024 No Access for Inspection RAUL OLAGI
Excavation/Setback/Form/Re-Bar 2/16/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 2/16/2024 Partial Approval RAUL OLAGI
Sewer 2/16/2024 Approved RAUL OLAGI
Underground Mechanical 2/16/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 2/23/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 2/28/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 3/4/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/19/2024 Partial Inspection RAUL OLAGI
Special/Order Compliance 3/19/2024 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/30/2024 Conditional Approval RAUL OLAGI
BUILDING-Rough-Frame 5/8/2024 Approved RAUL OLAGI
Green Building Rough 5/8/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 5/8/2024 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 5/8/2024 Approved RAUL OLAGI
Shower Pan 5/8/2024 Approved RAUL OLAGI
Insulation 5/20/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 5/20/2024 Approved RAUL OLAGI
Drywall Nailing 5/29/2024 Approved SALVADOR MARTINEZ
Final 3/19/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 3/19/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Final 3/19/2025 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Approved GAREN HAYRAPETYAN
Smoke Detectors 3/19/2025 Approved GAREN HAYRAPETYAN
Final 3/25/2025 Partial Inspection GAREN HAYRAPETYAN
Green Building Final 3/25/2025 Approved GAREN HAYRAPETYAN
Final 4/4/2025 OK to Issue CofO SALVADOR MARTINEZ
PLUMBING-Final 4/4/2025 Approved SALVADOR MARTINEZ
Service/Power Release 4/4/2025 Approved SALVADOR MARTINEZ