7731 N MASON AVE 91306
Certificate Information: 7731 N MASON AVE 91306
- Application / Permit
- 23014-20000-01584
- Plan Check / Job No.
- B23VN05191
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan**Addition to and Conversion of Existing Detached Garage at Rear of the Lot to an Accessory Dwelling Unit Per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 8/15/2023
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2023 | EDWIN ESPIN |
| Corrections Issued | 5/1/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 7/11/2023 | DANIEL YIP |
| Plan Check Approved | 8/10/2023 | ZAW HAN |
| Issued | 8/15/2023 | APPLICANT |
| CofO in Progress | 3/11/2024 | ARUTYUN MADATYAN |
| Permit Finaled | 4/18/2024 | JOHN JANSON |
| CofO Issued | 4/18/2024 | JOHN JANSON |
| Permit Finaled | 4/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2023 | RYAN KIM |
| Sewer availability | Cleared | 6/12/2023 | RYAN KIM |
| Low Impact Development (LID) | Cleared | 7/6/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 7/10/2023 | RYAN KIM |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/20/2023 | Partial Approval | JEFFREY PARD |
| Deputy Drilled-In Anchors | 9/25/2023 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 9/26/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/9/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 11/9/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 11/9/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 11/9/2023 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 11/9/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/14/2023 | Approved | ALEXANDER HANDY |
| Shower Pan | 11/14/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/17/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 11/17/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 11/17/2023 | Approved | ALEXANDER HANDY |
| Insulation | 11/20/2023 | Approved | ALEXANDER HANDY |
| Service/Power Release | 11/20/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Drywall Nailing | 11/27/2023 | Approved | ALEXANDER HANDY |
| Final | 2/26/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 2/26/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 2/26/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 3/8/2024 | Approved | ARUTYUN MADATYAN |
| Final | 3/8/2024 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 3/8/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 3/8/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 3/8/2024 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 3/8/2024 | Approved | ARUTYUN MADATYAN |