4713 N PLACIDIA AVE 91602
Certificate Information: 4713 N PLACIDIA AVE 91602
- Application / Permit
- 23014-20000-01578
- Plan Check / Job No.
- B23VN03717
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan - Converting detached Garage To An ADU + Addition per Gov't Code Section 65852.2(e)1(A)
- Permit Issued
- Issued on 10/9/2023
- Issuing Office
- Current Status
- CofO Issued on 11/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 3/30/2023 | SAM CHANG |
| Corrections Issued | 4/21/2023 | SAM CHANG |
| Quality Review Completed | 4/25/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/5/2023 | SAM CHANG |
| Plan Check Approved | 7/7/2023 | SAM CHANG |
| Issued | 10/9/2023 | APPLICANT |
| CofO in Progress | 8/13/2024 | JOSE AVILA |
| CofO in Progress | 10/11/2024 | JUAN VALENZUELA |
| No Progress | 10/11/2024 | JUAN VALENZUELA |
| CofO Issued | 11/13/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/13/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/31/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 6/8/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/8/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 6/9/2023 | MATTHEW CRAIG |
| Sewer availability | Cleared | 6/9/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/9/2023 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/13/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/13/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 11/13/2023 | Partial Approval | JENNIFER RABUCHIN |
| Underground Mechanical | 11/13/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/11/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| Green Building Rough | 12/11/2023 | No Access for Inspection | JENNIFER RABUCHIN |
| Wood Frame | 12/11/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/19/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 1/19/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/24/2024 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/27/2024 | Partial Inspection | CRAIG DAVIS |
| Green Building Rough | 2/27/2024 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 3/5/2024 | Approved | JOHN HAYES |
| Green Building Rough | 3/5/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/5/2024 | Partial Approval | JOHN HAYES |
| Shower Pan | 3/6/2024 | Approved | JOHN HAYES |
| Insulation | 3/8/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 3/15/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/20/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 3/22/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 7/17/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 7/19/2024 | Approved | JOSE AVILA |
| Gas Test | 7/19/2024 | Approved | JOSE AVILA |
| HVAC-Final | 7/19/2024 | Approved | JOSE AVILA |
| PLUMBING-Final | 7/19/2024 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 7/19/2024 | SGSOV Approved | JOSE AVILA |
| Final | 8/12/2024 | OK to Issue CofO | JOSE AVILA |
| Green Building Final | 8/12/2024 | Approved | JOSE AVILA |
| Smoke Detectors | 8/12/2024 | Approved | JOSE AVILA |
| Special/Order Compliance | 10/11/2024 | Corrections Issued | JOSE AVILA |