13463 W HERRON ST 91342
Certificate Information: 13463 W HERRON ST 91342
- Application / Permit
- 23014-20000-01574
- Plan Check / Job No.
- B23VN05175
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 44' X 27' ADDITION TO (E) SINGLE-FAMILY DWELLING
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2023 | SERGIO MUNIZ |
| Corrections Issued | 4/27/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/28/2023 | APPLICANT |
| Applicant returned to address corrections | 6/2/2023 | ALEC MOUSAKHANIAN |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 3/8/2024 | KEVIN BERBERYAN |
| Permit Finaled | 3/19/2024 | RUBEN SALAS |
| CofO Issued | 3/19/2024 | RUBEN SALAS |
| Permit Finaled | 3/19/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/3/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2023 | RYAN KIM |
| Low Impact Development (LID) | Cleared | 6/1/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 6/1/2023 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 7/14/2023 | Not Ready for Inspection | RAUL OLAGI |
| Sewer | 7/14/2023 | Not Ready for Inspection | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 9/12/2023 | Corrections Issued | ROBERT GOLD |
| Footing/Foundation/Slab | 9/12/2023 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Rough | 9/12/2023 | Partial Approval | ROBERT GOLD |
| Sewer | 9/12/2023 | Corrections Issued | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 9/18/2023 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 9/18/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/18/2023 | Approved | KEVIN BERBERYAN |
| Sewer | 9/18/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/25/2023 | Conditional Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/25/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 10/25/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Rough | 10/25/2023 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/25/2023 | Corrections Issued | KEVIN BERBERYAN |
| Sewer | 10/25/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/3/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 11/3/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 11/3/2023 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/3/2023 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/3/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 11/8/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/8/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Shower Pan | 11/8/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 11/13/2023 | Approved | KEVIN BERBERYAN |
| Final | 12/6/2023 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 12/6/2023 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 12/6/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 3/8/2024 | Approved | KEVIN BERBERYAN |
| Final | 3/8/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| HVAC-Final | 3/8/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 3/8/2024 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 3/8/2024 | Approved | KEVIN BERBERYAN |