7231 N OSTROM AVE 91406

Certificate Information: 7231 N OSTROM AVE 91406

Application / Permit
23014-20000-01543
Plan Check / Job No.
B23VN05050
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan (N) 13'-7" x 13'-4" ADDITION TO (E) SFD PER ENGINEERING
Permit Issued
Issued on 6/21/2023
Issuing Office
Current Status
CofO Issued on 4/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/20/2023 APPLICANT
Assigned to Plan Check Engineer 4/25/2023 ISIS ARGUETA
Corrections Issued 4/26/2023 ISIS ARGUETA
Plan Check Approved 5/31/2023 ISIS ARGUETA
Issued 6/21/2023 APPLICANT
CofO in Progress 1/24/2024 RAUL OLAGI
Permit Finaled 4/15/2024 DANIEL ORRANTE
Permit Finaled 4/15/2024 DANIEL ORRANTE
CofO Issued 4/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 5/1/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/2/2023 CARLOS AGUILERA

Contact Information

Contractor Lydios Construction Inc; Lic. No.: 1007190-B 14207 POLK STREET      SYLMAR, CA 91342
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/26/2023 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 7/5/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 7/13/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 7/13/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 7/20/2023 Partial Approval JUAN VALENZUELA
Insulation 7/20/2023 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 8/31/2023 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Partial Approval RAUL OLAGI
HVAC-Rough 8/31/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 8/31/2023 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 9/7/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 9/7/2023 Approved RAUL OLAGI
HVAC-Rough 9/7/2023 Approved RAUL OLAGI
PLUMBING-Rough 9/7/2023 Approved RAUL OLAGI
Insulation 9/15/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 9/15/2023 Approved RAUL OLAGI
Drywall Nailing 9/20/2023 Approved JACK KARGODORIAN
ELECTRICAL-Final 12/4/2023 Approved RAUL OLAGI
Final 12/4/2023 Corrections Issued RAUL OLAGI
HVAC-Final 12/4/2023 Approved RAUL OLAGI
PLUMBING-Final 12/4/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 12/4/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 12/4/2023 Approved RAUL OLAGI
Final 1/24/2024 OK to Issue CofO RAUL OLAGI