12024 W HARTSOOK ST 91607
Certificate Information: 12024 W HARTSOOK ST 91607
- Application / Permit
- 23014-20000-01540
- Plan Check / Job No.
- B23VN05043
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL AND 33'-4" X 16'-0" (485 S.F) ADDITION TO (E) SFD. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 7/7/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 4/22/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 4/25/2023 | APPLICANT |
| Applicant returned to address corrections | 6/28/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 6/29/2023 | MIROOSH KHACHATOORIAN |
| Issued | 7/7/2023 | APPLICANT |
| CofO in Progress | 5/23/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
| CofO Issued | 6/3/2025 | RUBEN SALAS |
| Permit Finaled | 6/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Specific Plan | Cleared | 4/27/2023 | JOANNA MARROQUIN |
| ZI | Cleared | 4/27/2023 | JOANNA MARROQUIN |
| ZI | Cleared | 4/27/2023 | JOANNA MARROQUIN |
| Sewer availability | Cleared | 5/16/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 6/26/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 6/26/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Reuss Enterprises Corporation; Lic. No.: 637751-B | 23777 MULHOLAND HWY SPC #15 CALABASAS, CA 91302 |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/14/2023 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 7/19/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/4/2023 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 8/4/2023 | Approved | JACK KARGODORIAN |
| Insulation | 8/4/2023 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 8/4/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 10/23/2023 | Approved | RYAN SALAZAR |
| Deputy Drilled-In Anchors | 11/13/2023 | Conditional Approval | JUAN VALENZUELA |
| Insulation | 11/28/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 12/18/2023 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 12/18/2023 | Partial Approval | KIRK SANDERS |
| Shower Pan | 12/18/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 1/25/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/2/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 7/2/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Final | 7/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 7/23/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Final | 5/23/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |