6317 N TAMPA AVE 91335
Certificate Information: 6317 N TAMPA AVE 91335
- Application / Permit
- 23014-20000-01533
- Plan Check / Job No.
- B23VN05009
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20'-2" X 20'-2" DETACHED GARAGE AND ADD 21'-3" X 26'-6" IRREGULAR SHAPED 2-STORY TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/22/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | RAPHAEL ROSAS |
| Corrections Issued | 5/10/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 5/15/2023 | STEVEN KIM |
| Building Plans Picked Up | 5/16/2023 | APPLICANT |
| Plan Check Approved | 9/21/2023 | RAPHAEL ROSAS |
| Issued | 9/22/2023 | APPLICANT |
| CofO in Progress | 6/11/2025 | ALEXANDER HANDY |
| Permit Finaled | 12/13/2025 | MICHAEL PELHAM |
| CofO Issued | 12/13/2025 | MICHAEL PELHAM |
| Permit Finaled | 12/13/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 6/5/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/14/2023 | CARLOS AGUILERA |
| ZI | Cleared | 8/7/2023 | ASHLEY RODARTE |
| Low Impact Development (LID) | Cleared | 9/1/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/5/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/13/2023 | Partial Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 11/28/2023 | Conditional Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 2/2/2024 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2024 | Corrections Issued | MORRIS JACKSON |
| Underground Mechanical | 2/8/2024 | Approved | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2024 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Approved | ARUTYUN MADATYAN |
| Posting Pre-Inspection | 4/25/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/7/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/9/2024 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 5/9/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 5/14/2024 | Partial Approval | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 5/21/2024 | Partial Approval | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 7/9/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 7/9/2024 | Corrections Issued | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 7/11/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 7/11/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 7/19/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 7/29/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 9/5/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Shower Pan | 9/5/2024 | Approved | ARUTYUN MADATYAN |
| Service/Power Release | 11/8/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| ELECTRICAL-Final | 4/11/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Gas Test | 4/11/2025 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Final | 4/11/2025 | Not Ready for Inspection | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 4/11/2025 | SGSOV Not Ready | JUAN ALVARADO |
| Service/Power Release | 4/11/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Gas Test | 4/16/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 6/5/2025 | Approved | ALEXANDER HANDY |
| Final | 6/5/2025 | Corrections Issued | ALEXANDER HANDY |
| Footing/Foundation/Slab | 6/5/2025 | Approved | ALEXANDER HANDY |
| Green Building Final | 6/5/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 6/5/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 6/5/2025 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 6/5/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 6/5/2025 | Approved | ALEXANDER HANDY |
| Final | 6/9/2025 | OK to Issue CofO | ALEXANDER HANDY |
| PLUMBING-Final | 6/9/2025 | Approved | ALEXANDER HANDY |
| Service/Power Release | 6/9/2025 | Approved | ALEXANDER HANDY |