18944 W KESWICK ST 91335

Certificate Information: 18944 W KESWICK ST 91335

Application / Permit
23014-20000-01532
Plan Check / Job No.
B23VN05005
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: 21'10" X 22' (465.42 SF) IRREGULAR SHAPED ADDITION TO AND CONVERT 324.63 SF (E) PORTION OF DETACHED ACCESSSORY LIVING QUARTERS AND (N) ADDITION PORTION TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g) . REMAINING PORTION TO REMAIN AS ACCESSORY LIVING QUARTERS. ALL WORK PER ENGINEERING. NFPA-13D FIRE SPRINKLERS THRU-OUT. "COMPLY WITH DEPARTMENT ORDER effective date 02/21/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 6/6/2024
Issuing Office
Current Status
Issued on 6/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/30/2023 APPLICANT
Assigned to Plan Check Engineer 5/3/2023 OMAR GARNICA
Corrections Issued 5/4/2023 OMAR GARNICA
Applicant returned to address corrections 7/19/2023 OMAR GARNICA
Plan Check Approved 8/5/2023 OMAR GARNICA
Issued 6/6/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/7/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/7/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/20/2023 MEGAN GODINEZ
Sewer availability Cleared 6/20/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 8/1/2023 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Southerland,, Richard Charles; Lic. No.: NA88965       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/23/2024 No Access for Inspection JOEL GUARDADO
Pre-Inspection 8/2/2024 Not Ready for Inspection JOEL GUARDADO
Insulation 8/20/2024 Approved JOEL GUARDADO
Pre-Inspection 8/20/2024 Approved JOEL GUARDADO
Shower Pan 8/20/2024 Approved JOEL GUARDADO
BUILDING-Rough-Frame 1/14/2025 Not Ready for Inspection JOEL GUARDADO
Green Building Rough 1/14/2025 Partial Inspection JOEL GUARDADO
Footing/Foundation/Slab 1/22/2025 Partial Inspection JOEL GUARDADO
Drywall Nailing 2/7/2025 Not Ready for Inspection JOEL GUARDADO
Deputy Drilled-In Anchors 2/10/2025 Conditional Approval KIM BEAUCHAMP
Footing/Foundation/Slab 2/14/2025 Approved JOEL GUARDADO
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Partial Approval JEFFREY DIFIORE
PLUMBING-Rough 2/25/2025 Corrections Issued JEFFREY DIFIORE
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Approved JOEL GUARDADO
PLUMBING-Final 2/27/2025 Partial Inspection JOEL GUARDADO
Underground Mechanical 2/27/2025 Approved JOEL GUARDADO
ELECTRICAL-Rough 3/4/2025 Approved JOEL GUARDADO
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Inspection JOEL GUARDADO
PLUMBING-Final 3/4/2025 Not Ready for Inspection JOEL GUARDADO
BUILDING-Rough-Frame 3/14/2025 Approved JOEL GUARDADO
Green Building Rough 3/14/2025 Approved JOEL GUARDADO
Insulation 3/14/2025 Approved JOEL GUARDADO
PLUMBING-Final 3/14/2025 Not Ready for Inspection JOEL GUARDADO
Wood Frame 3/14/2025 Approved JOEL GUARDADO
Drywall Nailing 4/8/2025 Approved JOEL GUARDADO
PLUMBING-Final 4/8/2025 Not Ready for Inspection JOEL GUARDADO
Shower Pan 4/8/2025 Corrections Issued JOEL GUARDADO
Shower Pan 4/14/2025 Approved KIM BEAUCHAMP
Final 7/8/2025 Corrections Issued JOEL GUARDADO
Green Building Final 7/8/2025 Approved JOEL GUARDADO
SGSOV-Seismic Gas S/O Valve 7/8/2025 SGSOV Approved JOEL GUARDADO
Smoke Detectors 7/8/2025 Approved JOEL GUARDADO
Final 7/14/2025 Corrections Issued KIM BEAUCHAMP
PLUMBING-Final 7/14/2025 Not Ready for Inspection KIM BEAUCHAMP
Final 7/28/2025 Conditional Approval KIM BEAUCHAMP