7432 N SHOUP AVE 91307
Certificate Information: 7432 N SHOUP AVE 91307
- Application / Permit
- 23014-20000-01528
- Plan Check / Job No.
- B23VN05002
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE WITH (N) 12'-6" x 15'-0" ADDITION INTO A (N) IRREGULAR SHAPED 20'-0" x 35'-2" DETACHED ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d) PER ENGINEERING
- Permit Issued
- Issued on 11/4/2023
- Issuing Office
- Current Status
- CofO Issued on 10/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2023 | ALFRED RAMIREZ |
| Corrections Issued | 4/25/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 11/2/2023 | ALFRED RAMIREZ |
| Issued | 11/4/2023 | APPLICANT |
| CofO in Progress | 10/22/2024 | CHRIS CHRISTENSEN |
| Permit Finaled | 10/25/2024 | JOHN JANSON |
| CofO Issued | 10/25/2024 | JOHN JANSON |
| Permit Finaled | 10/25/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2023 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 5/4/2023 | RYAN KIM |
| Sewer availability | Cleared | 5/8/2023 | RYAN KIM |
| Eng Process Fee Ord 176,300 | Cleared | 5/18/2023 | RYAN KIM |
| Construction near power lines | Cleared | 10/3/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/17/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 11/28/2023 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 11/28/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/29/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/29/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/29/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 1/2/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/2/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2024 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 1/2/2024 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/22/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 1/22/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 1/22/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/22/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 1/29/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/29/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/8/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/8/2024 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 7/25/2024 | Approved | JEFFREY PARD |
| Gas Test | 7/25/2024 | Corrections Issued | JEFFREY PARD |
| PLUMBING-Rough | 7/25/2024 | Corrections Issued | JEFFREY PARD |
| Gas Test | 7/29/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 8/23/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/23/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/23/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 10/7/2024 | No Access for Inspection | CHRIS CHRISTENSEN |
| Final | 10/11/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 10/21/2024 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 10/21/2024 | Approved | CHRIS CHRISTENSEN |