8101-8105 N MELBA AVE 91304

Certificate Information: 8101-8105 N MELBA AVE 91304

Application / Permit
23014-20000-01524
Plan Check / Job No.
B23VN04999
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and convert portion of (E) SFD to 393 sf ADU per LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 5/18/2023
Issuing Office
Current Status
CofO Issued on 12/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2023 APPLICANT
Assigned to Plan Check Engineer 4/24/2023 VICTOR CHEN
Corrections Issued 4/25/2023 VICTOR CHEN
Applicant returned to address corrections 5/16/2023 SHANGQIN XIE
Plan Check Approved 5/17/2023 SHANGQIN XIE
Issued 5/18/2023 APPLICANT
CofO in Progress 12/13/2023 CHRIS CHRISTENSEN
Permit Finaled 12/27/2023 JOHN JANSON
CofO Issued 12/27/2023 JOHN JANSON
Permit Finaled 12/27/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/1/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/1/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/3/2023 CARLOS AGUILERA
Sewer availability Cleared 5/3/2023 CARLOS AGUILERA
Grading Pre-Inspection Cleared 5/9/2023 ROBERT PINA

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316
Engineer Mohammadi,, Saeid; Lic. No.: NA82330       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 5/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/22/2023 Partial Approval CHRIS CHRISTENSEN
Pre-Inspection 5/22/2023 Approved CHRIS CHRISTENSEN
Sewer 5/22/2023 Partial Approval CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 6/16/2023 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/16/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Final 6/16/2023 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 6/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 6/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 6/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 6/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Deputy Wood Construction 6/26/2023 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/26/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/26/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 6/26/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 6/26/2023 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/27/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 6/27/2023 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 6/27/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 6/27/2023 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/29/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 6/29/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 6/29/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 6/29/2023 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 6/29/2023 Approved CHRIS CHRISTENSEN
Shower Pan 6/29/2023 Approved CHRIS CHRISTENSEN
Insulation 7/3/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/3/2023 Not Ready for Inspection MORRIS JACKSON
Drywall Nailing 7/10/2023 Approved HORACE FULTZ
Final 10/4/2023 Corrections Issued CHRIS CHRISTENSEN
Gas Test 10/4/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 10/4/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 10/4/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 10/4/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Smoke Detectors 10/4/2023 Approved CHRIS CHRISTENSEN
Final 10/31/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 10/31/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved CHRIS CHRISTENSEN
Final 12/12/2023 OK to Issue CofO CHRIS CHRISTENSEN