8101-8105 N MELBA AVE 91304
Certificate Information: 8101-8105 N MELBA AVE 91304
- Application / Permit
- 23014-20000-01524
- Plan Check / Job No.
- B23VN04999
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and convert portion of (E) SFD to 393 sf ADU per LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 5/18/2023
- Issuing Office
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2023 | VICTOR CHEN |
| Corrections Issued | 4/25/2023 | VICTOR CHEN |
| Applicant returned to address corrections | 5/16/2023 | SHANGQIN XIE |
| Plan Check Approved | 5/17/2023 | SHANGQIN XIE |
| Issued | 5/18/2023 | APPLICANT |
| CofO in Progress | 12/13/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 12/27/2023 | JOHN JANSON |
| CofO Issued | 12/27/2023 | JOHN JANSON |
| Permit Finaled | 12/27/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2023 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/1/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/3/2023 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 5/9/2023 | ROBERT PINA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
| Engineer | Mohammadi,, Saeid; Lic. No.: NA82330 | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 5/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 5/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 5/22/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Inspection | 5/22/2023 | Approved | CHRIS CHRISTENSEN |
| Sewer | 5/22/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/16/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/16/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 6/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 6/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 6/26/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/26/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/26/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/26/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Wood Frame | 6/26/2023 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/27/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 6/27/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/27/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/27/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/29/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/29/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 6/29/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/29/2023 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 6/29/2023 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 6/29/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 7/3/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 7/3/2023 | Not Ready for Inspection | MORRIS JACKSON |
| Drywall Nailing | 7/10/2023 | Approved | HORACE FULTZ |
| Final | 10/4/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Gas Test | 10/4/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 10/4/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Final | 10/4/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Service/Power Release | 10/4/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 10/4/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 10/31/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 10/31/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 10/31/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 12/12/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |