14442 W SAYRE ST 91342
Certificate Information: 14442 W SAYRE ST 91342
- Application / Permit
- 23014-20000-01522
- Plan Check / Job No.
- B23VN04997
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 20'-0" X 22'-0" ADDITION AND CONVERT EXISTING 19'-6" X 21'-0" DETACHED GARAGE INTO ACCESSORY DWELLIGN UNIT PER LAMC 12.22 A.33(c) AND (d) - WORK DONE PER WFPP.
- Permit Issued
- Issued on 2/7/2024
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/28/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 5/1/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 9/28/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 2/5/2024 | SARKIS HARABEDIAN |
| Issued | 2/7/2024 | APPLICANT |
| CofO in Progress | 10/3/2025 | JENNIFER RABUCHIN |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2023 | RYAN KIM |
| Roof/Waste drainage to street | Cleared | 6/9/2023 | RYAN KIM |
| Construction near power lines | Cleared | 9/12/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/12/2023 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2023 | RYAN KIM |
| Sewer availability | Cleared | 9/19/2023 | RYAN KIM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/15/2024 | Partial Approval | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 7/29/2024 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 7/29/2024 | Partial Inspection | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 7/31/2024 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 7/31/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 1/7/2025 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 1/7/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 1/7/2025 | Partial Approval | JACK KARGODORIAN |
| ELECTRICAL-Rough | 2/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/20/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 2/20/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/26/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 2/26/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/26/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/12/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/14/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/14/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 3/14/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/14/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 3/25/2025 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/21/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/21/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 4/21/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 6/11/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 9/3/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Green Building Final | 9/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 9/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Final | 9/8/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/8/2025 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Final | 9/19/2025 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/19/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Final | 9/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 10/2/2025 | Approved | JENNIFER RABUCHIN |
| Final | 10/2/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 10/2/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/2/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/2/2025 | Approved | JENNIFER RABUCHIN |