9649 N VALJEAN AVE 91343
Certificate Information: 9649 N VALJEAN AVE 91343
- Application / Permit
- 23014-20000-01520
- Plan Check / Job No.
- B23VN04995
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF (FRONT) 7'-8" x 23'-11" WITH PORCH AND (REAR) 10'-0" x 48'-11 TO (E) S.F.D. PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 04/26/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/12/2023
- Issuing Office
- Current Status
- Pending
- Certificate of Occupancy
- CofO Issued More Information
Pre - Inspection only, not a permit for construction
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 4/21/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/24/2023 | APPLICANT |
| Issued | 6/12/2023 | APPLICANT |
| CofO in Progress | 10/10/2023 | MARK DOVICO |
| CofO Issued | 11/8/2023 | DAVID JAMES |
| Permit Finaled | 11/8/2023 | DAVID JAMES |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | NIKKI ZULUETA |
| GPI Written Notices | Cleared | 6/12/2023 | JEROME MAGAT PALMA |
| Grading Pre-Inspection | Cleared | 6/12/2023 | JEROME MAGAT PALMA |
| Low Impact Development (LID) | Cleared | 6/12/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 6/12/2023 | COLIN LOREDO |
| Grading Preinspection | Not Cleared | 9/29/2023 | Department of Building and Safety |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/14/2023 | Approved | MARK DOVICO |
| Underground Mechanical | 6/14/2023 | Approved | MARK DOVICO |
| ELECTRICAL-Rough | 7/21/2023 | Approved | JOHN STEPHENS |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Approved | JOHN STEPHENS |
| HVAC-Rough | 7/21/2023 | Approved | JOHN STEPHENS |
| BUILDING-Rough-Frame | 7/28/2023 | Not Ready for Inspection | JOHN STEPHENS |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2023 | Not Ready for Inspection | JOHN STEPHENS |
| Green Building Rough | 7/28/2023 | Approved | JOHN STEPHENS |
| PLUMBING-Rough | 7/28/2023 | Partial Approval | JOHN STEPHENS |
| PLUMBING-Rough | 8/1/2023 | Approved | JOHN STEPHENS |
| Shower Pan | 8/1/2023 | Approved | JOHN STEPHENS |
| Insulation | 8/3/2023 | Approved | JOHN STEPHENS |
| Drywall Nailing | 8/8/2023 | Approved | JOHN STEPHENS |
| Interior/Exterior Lathing | 8/8/2023 | Approved | JOHN STEPHENS |
| BUILDING-Rough-Frame | 9/25/2023 | Approved | JOHN STEPHENS |
| Final | 9/25/2023 | No Access for Inspection | JOHN STEPHENS |
| Green Building Final | 9/25/2023 | Not Ready for Inspection | JOHN STEPHENS |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Not Ready | JOHN STEPHENS |
| Smoke Detectors | 9/25/2023 | No Access for Inspection | JOHN STEPHENS |
| ELECTRICAL-Final | 9/28/2023 | Corrections Issued | MARK DOVICO |
| Excavation/Setback/Form/Re-Bar | 9/28/2023 | Approved | MARK DOVICO |
| Gas Test | 9/28/2023 | Not Ready for Inspection | MARK DOVICO |
| Green Building Final | 9/28/2023 | Corrections Issued | MARK DOVICO |
| HVAC-Final | 9/28/2023 | Corrections Issued | MARK DOVICO |
| PLUMBING-Final | 9/28/2023 | Not Ready for Inspection | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | MARK DOVICO |
| Smoke Detectors | 9/28/2023 | Approved | MARK DOVICO |
| ELECTRICAL-Final | 10/3/2023 | Corrections Issued | MARK DOVICO |
| Final | 10/3/2023 | Corrections Issued | MARK DOVICO |
| Gas Test | 10/3/2023 | Partial Inspection | MARK DOVICO |
| HVAC-Final | 10/3/2023 | Conditional Approval | MARK DOVICO |
| PLUMBING-Final | 10/3/2023 | Corrections Issued | MARK DOVICO |
| Final | 10/5/2023 | Conditional Approval | MARK DOVICO |
| Green Building Final | 10/5/2023 | Approved | MARK DOVICO |