14401 W MERCER ST 91331
Certificate Information: 14401 W MERCER ST 91331
- Application / Permit
- 23014-20000-01498
- Plan Check / Job No.
- B23VN04907
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'-3" X 6'-0" ADDITION OF LAUNDRY ROOM TO EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
- Permit Issued
- Issued on 5/26/2023
- Issuing Office
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 4/18/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 5/25/2023 | DANIEL ABRAMYAN |
| Issued | 5/26/2023 | APPLICANT |
| CofO in Progress | 9/22/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
| CofO Issued | 12/21/2023 | RUBEN SALAS |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 4/22/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Jennifer Arianna; Lic. No.: C79156 | 3828 EARLE AVE ROSEMEAD, CA 91770 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/2/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| METHANE-Barrier | 8/2/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 8/2/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 8/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Rough | 8/8/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 8/8/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/29/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 8/29/2023 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/29/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/29/2023 | Approved | JENNIFER RABUCHIN |
| Insulation | 9/1/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/1/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/7/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 9/21/2023 | Approved | JENNIFER RABUCHIN |
| Final | 9/21/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/21/2023 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 9/21/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 9/21/2023 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 9/21/2023 | Approved | JENNIFER RABUCHIN |