14401 W MERCER ST 91331

Certificate Information: 14401 W MERCER ST 91331

Application / Permit
23014-20000-01498
Plan Check / Job No.
B23VN04907
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12'-3" X 6'-0" ADDITION OF LAUNDRY ROOM TO EXISTING SINGLE FAMILY DWELLING - PER ENGINEER
Permit Issued
Issued on 5/26/2023
Issuing Office
Current Status
CofO Issued on 12/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2023 APPLICANT
Assigned to Plan Check Engineer 4/18/2023 DANIEL ABRAMYAN
Corrections Issued 4/18/2023 DANIEL ABRAMYAN
Plan Check Approved 5/25/2023 DANIEL ABRAMYAN
Issued 5/26/2023 APPLICANT
CofO in Progress 9/22/2023 JENNIFER RABUCHIN
Permit Finaled 12/21/2023 RUBEN SALAS
CofO Issued 12/21/2023 RUBEN SALAS
Permit Finaled 12/21/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/22/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 4/25/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Jennifer Arianna; Lic. No.: C79156 3828 EARLE AVE      ROSEMEAD, CA 91770

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/2/2023 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Barrier 8/2/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 8/2/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/8/2023 Corrections Issued JENNIFER RABUCHIN
Insulation 8/8/2023 Partial Approval JENNIFER RABUCHIN
METHANE-Rough 8/8/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 8/8/2023 Partial Approval JENNIFER RABUCHIN
Wood Frame 8/8/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/29/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 8/29/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/29/2023 Approved JENNIFER RABUCHIN
Green Building Rough 8/29/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 8/29/2023 Approved JENNIFER RABUCHIN
Insulation 9/1/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 9/1/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 9/7/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/21/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/21/2023 Approved JENNIFER RABUCHIN
Final 9/21/2023 OK to Issue CofO JENNIFER RABUCHIN
Footing/Foundation/Slab 9/21/2023 Approved JENNIFER RABUCHIN
HVAC-Final 9/21/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/21/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 9/21/2023 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 9/21/2023 Approved JENNIFER RABUCHIN