15823 W DEVONSHIRE ST 91311
Certificate Information: 15823 W DEVONSHIRE ST 91311
- Application / Permit
- 23014-20000-01493
- Plan Check / Job No.
- B23VN04891
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 32'-0" X 28'-0" ADDITION OF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) TO EXISTING DETACHED GARAGE - PER ENGINEER
- Permit Issued
- Issued on 8/16/2023
- Issuing Office
- Current Status
- CofO Issued on 10/28/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 4/22/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 6/20/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 7/28/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 8/1/2023 | ANDREW SANTIAGO |
| Issued | 8/16/2023 | APPLICANT |
| CofO in Progress | 10/25/2024 | ROBERT GOLD |
| Permit Finaled | 10/28/2024 | DANIEL ORRANTE |
| CofO Issued | 10/28/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2023 | ANA SORIANO |
| Sewer availability | Cleared | 5/19/2023 | ANA SORIANO |
| Low Impact Development (LID) | Cleared | 7/26/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 7/27/2023 | ANA SORIANO |
Contact Information
| Contractor | Pristine General Contracting Corp; Lic. No.: 1072946-B | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/21/2023 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 8/30/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 8/31/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 9/5/2023 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 9/13/2023 | No Access for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 9/14/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/22/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/3/2023 | No Access for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/13/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/13/2023 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 11/13/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/13/2023 | Partial Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 11/16/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 11/17/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/17/2023 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/30/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/13/2023 | Partial Inspection | JAVIER RAMOS JR |
| Insulation | 12/13/2023 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Rough | 12/15/2023 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 12/15/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 12/19/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 12/21/2023 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 2/9/2024 | Partial Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 4/12/2024 | No Access for Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 5/6/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Not Ready | JAVIER RAMOS JR |
| Final | 5/21/2024 | No Access for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 5/21/2024 | No Access for Inspection | JAVIER RAMOS JR |
| Special/Order Compliance | 6/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 6/11/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/18/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/18/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/1/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/10/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/10/2024 | Approved | JAVIER RAMOS JR |
| Green Building Final | 7/10/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 7/10/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 7/10/2024 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 7/10/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/16/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 7/16/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 9/6/2024 | Approved | KEVIN BERBERYAN |
| Final | 9/6/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV No Gas | KEVIN BERBERYAN |
| Smoke Detectors | 9/6/2024 | Approved | KEVIN BERBERYAN |