14103 W PIERCE ST 91331
Certificate Information: 14103 W PIERCE ST 91331
- Application / Permit
- 23014-20000-01491
- Plan Check / Job No.
- B23VN04890
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION TO (E) 1-STORY ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 6/2/2023
- Issuing Office
- Current Status
- CofO Issued on 3/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | DANIEL YIP |
| Corrections Issued | 5/17/2023 | DANIEL YIP |
| Quality Review Completed | 5/17/2023 | GARO TELMI |
| Plan Check Approved | 6/2/2023 | DANIEL YIP |
| Issued | 6/2/2023 | APPLICANT |
| CofO in Progress | 12/27/2023 | MICHEL ABAJAN |
| Permit Finaled | 3/21/2024 | RUBEN SALAS |
| CofO Issued | 3/21/2024 | RUBEN SALAS |
| Permit Finaled | 3/21/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/20/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/22/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/28/2023 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 8/28/2023 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 8/28/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 9/22/2023 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 9/22/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 9/22/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 9/22/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 10/16/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/16/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 10/16/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/16/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 10/16/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 10/27/2023 | Approved | MICHEL ABAJAN |
| Insulation | 10/27/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/27/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/9/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 12/19/2023 | Approved | MICHEL ABAJAN |
| Final | 12/19/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 12/19/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 12/19/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 12/19/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/19/2023 | Approved | MICHEL ABAJAN |
| Final | 12/26/2023 | OK to Issue CofO | MICHEL ABAJAN |