13960 W FOX ST 91340
Certificate Information: 13960 W FOX ST 91340
- Application / Permit
- 23014-20000-01486
- Plan Check / Job No.
- B23VN04863
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 31'X18' DET GARAGE/ REC RM BLDG INTO ACCESSORY DWELLING UNIT WITH 10'-6" X 13'-6" ADDITION PER LAMC 12.22A.33 (c) & (d) REFRAME (E) ROOF OVER (E) GARAGE. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2023 | HAYATO TSUCHIYA |
| Corrections Issued | 4/19/2023 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 4/25/2023 | APPLICANT |
| Applicant returned to address corrections | 5/19/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/8/2023 | JEROME MAGAT PALMA |
| Issued | 6/8/2023 | APPLICANT |
| CofO in Progress | 3/5/2024 | JAVIER RAMOS JR |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
| CofO Issued | 4/3/2024 | RUBEN SALAS |
| Permit Finaled | 4/3/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2023 | NIKKI ZULUETA |
| Clean Up Green Up | Cleared | 5/2/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 5/16/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 5/23/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/2/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 8/2/2023 | Partial Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 10/2/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/2/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/7/2023 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/16/2023 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/16/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 11/16/2023 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Rough | 11/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/16/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 11/22/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/22/2023 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 11/28/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 11/28/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/5/2023 | Approved | MATTHEW NELSON |
| Sewer | 12/8/2023 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 12/13/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 12/20/2023 | Partial Approval | KEVIN BERBERYAN |
| Pre-Inspection | 1/18/2024 | No Access for Inspection | RUBEN SALAS |
| Underground Mechanical | 1/22/2024 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/22/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Drywall Nailing | 2/22/2024 | Corrections Issued | CRAIG DAVIS |
| Final | 2/22/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Final | 2/22/2024 | Corrections Issued | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 2/22/2024 | Approved | CRAIG DAVIS |
| Drywall Nailing | 2/27/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 2/27/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 2/27/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 2/27/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 3/4/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 3/4/2024 | Approved | JAVIER RAMOS JR |
| Final | 3/4/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 3/4/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 3/4/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 3/4/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 3/4/2024 | Approved | JAVIER RAMOS JR |