9849 W PORTOLA DR 90210

Certificate Information: 9849 W PORTOLA DR 90210

Application / Permit
23014-20000-01446
Plan Check / Job No.
B23VN04724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 3'-8" X 17'-2" ADDITION AND INTERIOR REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/22/2023
Issuing Office
Current Status
CofO Issued on 10/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2023 APPLICANT
Assigned to Plan Check Engineer 4/20/2023 RAPHAEL ROSAS
Corrections Issued 4/24/2023 RAPHAEL ROSAS
Quality Review Completed 4/27/2023 STEVEN KIM
Building Plans Picked Up 4/28/2023 APPLICANT
Plan Check Approved 5/22/2023 RAPHAEL ROSAS
Issued 5/22/2023 APPLICANT
CofO in Progress 10/25/2023 BRENDAN LOONEY
Permit Finaled 10/28/2023 DANIEL ORRANTE
CofO Issued 10/28/2023 DANIEL ORRANTE
Permit Finaled 10/28/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/1/2023 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 5/1/2023 ANTHONY MAINEZ
Sewer availability Cleared 5/1/2023 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 5/5/2023 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Mohammadi,, Saeid; Lic. No.: C82330 17412 VENTUTRA BLVD 21      ENCINO, CA 91316

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/25/2023 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Not Ready for Inspection STEPHANIE SWANSON
Footing/Foundation/Slab 5/25/2023 Corrections Issued STEPHANIE SWANSON
Pre-Inspection 5/25/2023 Approved STEPHANIE SWANSON
Deputy Wood Construction 6/7/2023 Conditional Approval BRENDAN LOONEY
BUILDING-Rough-Frame 6/21/2023 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 6/21/2023 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 6/21/2023 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 6/21/2023 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 6/21/2023 Partial Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 6/27/2023 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 7/3/2023 Partial Approval BRENDAN LOONEY
HVAC-Rough 7/3/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 7/12/2023 Not Ready for Inspection MICHAEL PELHAM
ELECTRICAL-Rough 7/12/2023 Not Ready for Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Approved MICHAEL PELHAM
Green Building Rough 7/12/2023 Not Ready for Inspection MICHAEL PELHAM
PLUMBING-Rough 7/12/2023 Approved MICHAEL PELHAM
ELECTRICAL-Rough 7/21/2023 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 7/25/2023 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 7/25/2023 Conditional Approval BRENDAN LOONEY
Green Building Rough 7/25/2023 Not Ready for Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 7/28/2023 Partial Approval BRENDAN LOONEY
Interior/Exterior Lathing 7/28/2023 Corrections Issued BRENDAN LOONEY
Insulation 8/3/2023 Conditional Approval BRENDAN LOONEY
Shower Pan 8/7/2023 Not Ready for Inspection STEPHANIE SWANSON
Drywall Nailing 8/15/2023 Conditional Approval BRENDAN LOONEY
Green Building Rough 8/15/2023 Partial Approval BRENDAN LOONEY
Shower Pan 8/15/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 8/21/2023 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 8/22/2023 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 8/29/2023 Approved BRENDAN LOONEY
Green Building Rough 8/29/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 8/29/2023 Approved BRENDAN LOONEY
Drywall Nailing 10/16/2023 Approved BRENDAN LOONEY
ELECTRICAL-Final 10/16/2023 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 10/16/2023 Approved BRENDAN LOONEY
Gas Test 10/16/2023 Approved BRENDAN LOONEY
Green Building Final 10/16/2023 Approved BRENDAN LOONEY
HVAC-Final 10/16/2023 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 10/16/2023 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 10/16/2023 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Final 10/18/2023 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Final 10/20/2023 Corrections Issued BRENDAN LOONEY
Final 10/20/2023 Corrections Issued BRENDAN LOONEY
HVAC-Final 10/20/2023 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 10/20/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 10/20/2023 Approved BRENDAN LOONEY
ELECTRICAL-Final 10/24/2023 Approved BRENDAN LOONEY
Final 10/24/2023 OK to Issue CofO BRENDAN LOONEY
HVAC-Final 10/24/2023 Approved BRENDAN LOONEY
PLUMBING-Final 10/24/2023 Approved BRENDAN LOONEY