5064 N LLANO DR 1-2 91364
Certificate Information: 5064 N LLANO DR 1-2 91364
- Application / Permit
- 23014-20000-01414
- Plan Check / Job No.
- B23VN04623
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Conversion of storage space under existing single-family residence into a 669 SF accessory dwelling unit. FULLY SPRINKLERED THROUGHOUT
- Permit Issued
- Issued on 5/30/2023
- Issuing Office
- Current Status
- CofO Issued on 8/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2023 | JOE VO |
| Corrections Issued | 4/14/2023 | JOE VO |
| Quality Review Completed | 4/16/2023 | PRANITA SHAH |
| Plan Check Approved | 5/30/2023 | JOE VO |
| Issued | 5/30/2023 | APPLICANT |
| CofO in Progress | 8/14/2024 | MORRIS JACKSON |
| No Progress | 1/16/2025 | SEAN WIRCH |
| CofO in Progress | 1/16/2025 | SEAN WIRCH |
| Permit Finaled | 8/29/2025 | JOHN JANSON |
| Permit Finaled | 8/29/2025 | JOHN JANSON |
| CofO Issued | 8/29/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/19/2023 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 4/19/2023 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 4/19/2023 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 4/19/2023 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 4/19/2023 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 4/19/2023 | JOHN LIN |
| Street Frontage | Cleared | 4/19/2023 | JOHN LIN |
| Street width determination | Cleared | 4/19/2023 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 5/11/2023 | KURT CORRAL |
| BHO/Hillside ordinance | Cleared | 5/12/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/12/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 5/22/2023 | JOE VO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: NA53210 | , |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | No Access for Inspection | SEAN HAUPT |
| Interior/Exterior Lathing | 8/1/2023 | No Access for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Corrections Issued | SEAN WIRCH |
| Interior/Exterior Lathing | 8/3/2023 | Not Ready for Inspection | SEAN WIRCH |
| Special/Order Compliance | 8/25/2023 | Corrections Issued | SEAN WIRCH |
| BUILDING-Rough-Frame | 9/8/2023 | Not Ready for Inspection | PETER FOLLING |
| Deputy Drilled-In Anchors | 9/8/2023 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 9/8/2023 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 9/8/2023 | Approved | PETER FOLLING |
| Green Building Rough | 9/8/2023 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 9/8/2023 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 9/8/2023 | Not Ready for Inspection | PETER FOLLING |
| Verify Sprinkler Sign Off | 9/8/2023 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 9/13/2023 | Corrections Issued | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 9/13/2023 | Corrections Issued | PETER FOLLING |
| PLUMBING-Rough | 9/13/2023 | Corrections Issued | PETER FOLLING |
| Shower Pan | 9/13/2023 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 9/26/2023 | Not Ready for Inspection | PETER FOLLING |
| ELECTRICAL-Rough | 9/26/2023 | Corrections Issued | PETER FOLLING |
| Green Building Rough | 9/26/2023 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 9/26/2023 | Approved | PETER FOLLING |
| Insulation | 9/26/2023 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 9/26/2023 | Approved | PETER FOLLING |
| Shower Pan | 9/26/2023 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 9/29/2023 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 9/29/2023 | Approved | SEAN WIRCH |
| Green Building Rough | 9/29/2023 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 9/29/2023 | Approved | SEAN WIRCH |
| Insulation | 10/31/2023 | Approved | PETER FOLLING |
| Drywall Nailing | 11/16/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/26/2024 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Final | 2/26/2024 | Not Ready for Inspection | JEFFREY PARD |
| Final | 2/26/2024 | Corrections Issued | JEFFREY PARD |
| Green Building Final | 2/26/2024 | Not Ready for Inspection | JEFFREY PARD |
| HVAC-Final | 2/26/2024 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Final | 2/26/2024 | Not Ready for Inspection | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 2/26/2024 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 2/26/2024 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 4/23/2024 | No Access for Inspection | MORRIS JACKSON |
| Final | 4/23/2024 | No Access for Inspection | MORRIS JACKSON |
| Green Building Final | 4/23/2024 | No Access for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 4/23/2024 | SGSOV Not Ready | MORRIS JACKSON |
| Smoke Detectors | 4/23/2024 | No Access for Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/30/2024 | Approved | MORRIS JACKSON |
| Final | 4/30/2024 | Corrections Issued | MORRIS JACKSON |
| Green Building Final | 4/30/2024 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 4/30/2024 | SGSOV Not Ready | MORRIS JACKSON |
| Smoke Detectors | 4/30/2024 | Corrections Issued | MORRIS JACKSON |
| Final | 5/10/2024 | No Access for Inspection | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 5/10/2024 | SGSOV Not Ready | MORRIS JACKSON |
| Smoke Detectors | 5/10/2024 | No Access for Inspection | MORRIS JACKSON |
| Final | 5/14/2024 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 5/14/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/20/2024 | Corrections Issued | JOHN HAYES |
| Smoke Detectors | 5/20/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/28/2024 | Corrections Issued | JOHN HAYES |
| Smoke Detectors | 5/28/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 6/25/2024 | Corrections Issued | JOHN HAYES |
| Smoke Detectors | 6/25/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/9/2024 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 7/9/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/8/2024 | No Access for Inspection | JOHN HAYES |
| Smoke Detectors | 8/8/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/13/2024 | OK to Issue CofO | MORRIS JACKSON |
| Smoke Detectors | 8/13/2024 | Approved | MORRIS JACKSON |