4941 S BERRYMAN AVE 90230

Certificate Information: 4941 S BERRYMAN AVE 90230

Application / Permit
23014-20000-01401
Plan Check / Job No.
B23VN04565
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW 20' x 26'-6" DET. GARAGE AND 20' X 10'-11" RECROOM.
Permit Issued
Issued on 11/2/2023
Issuing Office
Valley
Current Status
Issued on 11/2/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/11/2023 APPLICANT
Assigned to Plan Check Engineer 4/14/2023 SERGIO MUNIZ
Corrections Issued 4/17/2023 SERGIO MUNIZ
Building Plans Picked Up 4/19/2023 APPLICANT
Plan Check Approved 11/2/2023 ANGELICA MARTINEZ
Issued 11/2/2023 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/5/2023 DARIN LAM
Specific Plan Cleared 7/17/2023 ALESSANDRO MERCURI
Miscellaneous Cleared 10/23/2023 DARIN LAM
Low Impact Development (LID) Cleared 10/31/2023 SHAHIN KHAZEY
Roof/Waste drainage to street Cleared 10/31/2023 ANTHONY MAINEZ

Contact Information

Contractor Green Design Builders Inc; Lic. No.: 1058542-B 1650 WESTWOOD BLVD #200      LOS ANGELES, CA 90024

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2023 Partial Inspection JESUS PINEDA
PLUMBING-Rough 1/16/2024 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 1/19/2024 Conditional Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 1/30/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Approved JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 3/20/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 4/9/2024 Partial Approval TEMISTOCLES CAAL
Insulation 4/22/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 4/30/2024 Approved JESUS RODRIGUEZ
Sewer 5/17/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 5/17/2024 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 5/22/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 8/6/2024 Approved JESUS RODRIGUEZ
Final 8/6/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 8/6/2024 Approved JESUS RODRIGUEZ
Green Building Rough 8/6/2024 Approved JESUS RODRIGUEZ
HVAC-Final 8/6/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 8/6/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/6/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 8/6/2024 Approved JESUS RODRIGUEZ