20213 W OXNARD ST 91367

Certificate Information: 20213 W OXNARD ST 91367

Application / Permit
23014-20000-01348
Plan Check / Job No.
B23VN04420
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 21'9"X16' BEDRM ADDN, 12'10"X11'3" ADDN TO EXPAND EX LIV RM, REDUCE THE SIZE OF EX BEDRM & ADD A TUB WITHIN EX BATHRM PER PLAN. CONSTRUCTION DESIGN PER ENGR.
Permit Issued
Issued on 4/27/2023
Issuing Office
Valley
Current Status
Issued on 4/27/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/7/2023 APPLICANT
Assigned to Plan Check Engineer 4/13/2023 HAYATO TSUCHIYA
Corrections Issued 4/13/2023 HAYATO TSUCHIYA
Building Plans Picked Up 4/17/2023 APPLICANT
Plan Check Approved 4/27/2023 ALEC MOUSAKHANIAN
Issued 4/27/2023 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/20/2023 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 4/27/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 4/27/2023 MEGAN GODINEZ
Sewer availability Cleared 4/27/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Manoukian,, Krikor Kerop; Lic. No.: C87010 2310 W MAGNOLIA BLVD STE A      BURBANK, CA 91506

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/2/2023 Approved HORACE FULTZ
Wood Frame 6/1/2023 Partial Approval ALEXANDER HANDY
BUILDING-Rough-Frame 6/2/2023 Not Ready for Inspection ALEXANDER HANDY
ELECTRICAL-Rough 6/2/2023 Partial Approval ALEXANDER HANDY
Green Building Rough 6/2/2023 Not Ready for Inspection ALEXANDER HANDY
HVAC-Rough 6/9/2023 Approved ALEXANDER HANDY
Insulation 6/9/2023 Not Ready for Inspection ALEXANDER HANDY
Interior/Exterior Lathing 6/9/2023 Not Ready for Inspection ALEXANDER HANDY
Drywall Nailing 6/12/2023 No Access for Inspection ALEXANDER HANDY
Green Building Rough 6/12/2023 No Access for Inspection ALEXANDER HANDY
Drywall Nailing 6/14/2023 Partial Approval ALEXANDER HANDY
Green Building Rough 6/14/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 6/14/2023 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 6/26/2023 Approved ALEXANDER HANDY
Shower Pan 6/26/2023 Corrections Issued ALEXANDER HANDY
Interior/Exterior Lathing 6/29/2023 Partial Approval HORACE FULTZ
BUILDING-Rough-Frame 8/18/2023 Approved ALEXANDER HANDY
Drywall Nailing 8/18/2023 Approved ALEXANDER HANDY
Final 8/18/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 8/18/2023 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 8/18/2023 Approved ALEXANDER HANDY