18845 W KIRKCOLM LANE 91326

Certificate Information: 18845 W KIRKCOLM LANE 91326

Application / Permit
23014-20000-01333
Plan Check / Job No.
B23VN04360
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE EX. ATTACHED SUNROOM AND REFRAME WITH ADDITION ( 12' X 8'-2" ) FOR FAMILY ROOM AND BATHROOM EXPANSION. WORK PER ENGINEER.
Permit Issued
Issued on 4/17/2023
Issuing Office
Current Status
CofO Issued on 9/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/6/2023 APPLICANT
Assigned to Plan Check Engineer 4/6/2023 ROSENDO MEDINA
Corrections Issued 4/6/2023 ROSENDO MEDINA
Plan Check Approved 4/17/2023 MOHAMMAD ESMAILI
Issued 4/17/2023 APPLICANT
CofO in Progress 9/11/2025 JEFFREY PARD
Permit Finaled 9/16/2025 JOHN JANSON
CofO Issued 9/16/2025 JOHN JANSON
Permit Finaled 9/16/2025 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/12/2023 KIRK LINKLATER
Roof/Waste drainage to street Cleared 4/12/2023 LEE GUILBEAUX
ZA Case Cleared 4/12/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 4/13/2023 LEE GUILBEAUX
Waste Hauler Permit Cleared 4/17/2023 MELINEH AGHAKHABIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/6/2023 Partial Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 7/12/2023 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 7/12/2023 Corrections Issued STEVEN BACK
Excavation/Setback/Form/Re-Bar 8/7/2023 Approved STEVEN BACK
Footing/Foundation/Slab 8/7/2023 Approved STEVEN BACK
ELECTRICAL-Rough 9/7/2023 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/7/2023 Corrections Issued STEVEN BACK
HVAC-Rough 9/7/2023 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 9/7/2023 Approved STEVEN BACK
Sewer 9/7/2023 Approved STEVEN BACK
BUILDING-Rough-Frame 9/19/2023 Approved STEVEN BACK
ELECTRICAL-Rough 9/19/2023 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/19/2023 Approved STEVEN BACK
Green Building Rough 9/19/2023 Approved STEVEN BACK
Insulation 9/19/2023 Partial Approval STEVEN BACK
Interior/Exterior Lathing 9/19/2023 Partial Approval STEVEN BACK
PLUMBING-Rough 9/19/2023 Approved STEVEN BACK
Insulation 9/21/2023 Approved STEVEN BACK
Drywall Nailing 9/29/2023 Partial Approval STEVEN BACK
Drywall Nailing 11/21/2023 Approved STEVEN BACK
Interior/Exterior Lathing 11/21/2023 Approved STEVEN BACK
Shower Pan 11/21/2023 Approved STEVEN BACK
Final 2/12/2024 Corrections Issued STEVEN BACK
Green Building Final 2/12/2024 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved STEVEN BACK
Smoke Detectors 2/12/2024 Approved STEVEN BACK
Final 9/10/2025 OK to Issue CofO JEFFREY PARD